Natural gasOperatingFPL

Oleander Power Project LP

Natural gas power plant in Brevard County, Florida. 994.4 MW of nameplate capacity across 5 generators, operated by Oleander Holdings LLC.

Also known as Oleander Plant · EIA plant 55286

Analyst: free account, 1 question a day.

BrevardCape CanaveralIndian River PlantSpace Coast Next Gen…Discovery Solar CenterOleander Power Project LP10 km
Open in the map
5 plants within 21 km, from EIA coordinates.

Key facts

Capacity
994.4 MWNameplate
Generators
5 operatingEIA-860M, August 2026
Operating since
June 2002First generator online
Operator
Oleander Holdings LLCEIA operator ID 61905
Grid
FPLBalancing authority FPL
Price nodes
None linkedNo verified ISO node
Location
Brevard County, FL28.3661, −80.7947
EIA plant ID
55286EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Oleander Power Project LP produces

Free · EIA-923

Net generation, 2025

580 GWh

579,648 MWh, final

Capacity factor, 2025

6.7%

2024: 5.6%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

98.2–579.6

GWh a year. Low 2020, high 2025

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002421,197Not reported9 of 12
2003920,184Not reported12 of 12
2004423,723Not reported12 of 12
2005304,125Not reported12 of 12
2006402,401Not reported12 of 12
2007547,075Not reported12 of 12
2008308,957Not reported12 of 12
2009522,266Not reported12 of 12
2010572,7476.6%12 of 12
2011361,7044.2%12 of 12
2012209,8032.4%12 of 12
201346,846Not reported12 of 12
201473,3470.8%12 of 12
2015257,3243.0%12 of 12
2016141,1731.6%12 of 12
2017155,4571.8%12 of 12
2018124,2401.4%12 of 12
2019189,3642.2%12 of 12
202098,1661.1%12 of 12
2021217,8982.5%12 of 12
2022408,5124.7%12 of 12
2023383,5774.4%12 of 12
2024488,8505.6%12 of 12
2025579,6486.7%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

CO₂, 2025

363,553

US short tons. 2024: 318,923

SO₂, 2025

8

US short tons

NOx, 2025

95

US short tons

CO₂ per MWh, calculated

0.63 t

About 1,254 lb per MWh

5 of 5 EPA units reported CO₂ in 2025 (O-1, O-2, O-3, O-4, O-5), matched to EIA plant 55286 through the EPA–EIA crosswalk. The per-MWh rate is EPA CO₂ divided by EIA-923 net generation. The two reporting boundaries can differ.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
OG1Natural Gas Fired Combustion Turbine198.9June 2002
OG2Natural Gas Fired Combustion Turbine198.9June 2002
OG3Natural Gas Fired Combustion Turbine198.9July 2002
OG4Natural Gas Fired Combustion Turbine198.9August 2002
OG5Natural Gas Fired Combustion Turbine198.8December 2007

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Oleander Holdings LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Oleander Power Project LP and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Oleander Power Project LP

Questions about Oleander Power Project LP

How much power does Oleander Power Project LP produce?

Oleander Power Project LP reported 579,648 MWh (580 GWh) of net generation in 2025, a 6.7% capacity factor on 994.4 MW of nameplate capacity.

Where is Oleander Power Project LP?

Oleander Power Project LP is in Brevard County, Florida, at 28.3661, −80.7947. It is in the Florida Power & Light Company balancing area (FPL).

Who operates Oleander Power Project LP?

EIA-860M for August 2026 lists Oleander Holdings LLC as the operator (EIA operator ID 61905). The operator is not always the owner.

When did Oleander Power Project LP start operating?

Its first generator began operating in June 2002, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • EPA CAMPD annual emissions through the EPA–EIA crosswalk, 1995 to 2025
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page