WindOperatingNYISO

Fenner Wind

Wind power plant in Madison County, New York. 30 MW of nameplate capacity across 1 generator, operated by CHI Energy Inc.

Also known as Fenner Wind Farm · Fenner Wind Power Project · Fenner Wind Power Project - Repower · EIA plant 55790

Analyst: free account, 1 question a day.

Madison CountyOwlville Creek Solar 2, LLCOwlville Creek Solar, LLCTwin Lantern Solar Pr…Fenner Wind5 km
Open in the map
6 plants within 12 km, from EIA coordinates.

Key facts

Capacity
30 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
October 2001First generator online
Operator
CHI Energy IncEIA operator ID 34688
Grid
NYISOBalancing authority NYIS
Price nodes
1 NYISO nodeResource nodes with prices
Location
Madison County, NY42.9890, −75.7625
EIA plant ID
55790EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Fenner Wind produces

Free · EIA-923

Net generation, 2025

75.8 GWh

75,750 MWh, final

Capacity factor, 2025

28.8%

2024: 24.4%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

44.4–87.1

GWh a year. Low 2017, high 2022

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
200246,490Not reported12 of 12
20036,888Not reported12 of 12
200478,376Not reported12 of 12
200567,750Not reported12 of 12
200677,273Not reported12 of 12
200772,190Not reported12 of 12
200870,930Not reported12 of 12
200964,112Not reported12 of 12
201026,0649.9%12 of 12
201165,00524.7%12 of 12
201258,56722.2%12 of 12
201368,25226.0%12 of 12
201467,94425.9%12 of 12
201567,35025.6%12 of 12
201662,45123.7%12 of 12
201744,44816.9%12 of 12
201853,87320.5%12 of 12
201979,12930.1%12 of 12
202062,12223.6%12 of 12
202173,37227.9%12 of 12
202287,08333.1%12 of 12
202370,42126.8%12 of 12
202464,36124.4%12 of 12
202575,75028.8%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · NYISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Onshore Wind Turbine30.0October 2001

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists CHI Energy Inc as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Fenner Wind and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Fenner Wind

Questions about Fenner Wind

How much power does Fenner Wind produce?

Fenner Wind reported 75,750 MWh (75.8 GWh) of net generation in 2025, a 28.8% capacity factor on 30 MW of nameplate capacity.

Where is Fenner Wind?

Fenner Wind is in Madison County, New York, at 42.9890, −75.7625. It is in the New York Independent System Operator balancing area (NYIS).

Who operates Fenner Wind?

EIA-860M for August 2026 lists CHI Energy Inc as the operator (EIA operator ID 34688). The operator is not always the owner.

When did Fenner Wind start operating?

Its first generator began operating in October 2001, according to EIA-860M.

Does InfraMap have power prices for Fenner Wind?

Yes. InfraMap has NYISO day-ahead and real-time prices at 1 price node linked to Fenner Wind, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • NYISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)
  • Project names from the USGS U.S. Wind Turbine Database

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page