Sandy Ridge Wind Farm

Wind power plant in Blair County, Pennsylvania. 50 MW of nameplate capacity across 1 generator, operated by Algonquin Power Co.

Also known as Sandy Ridge · EIA plant 57285

Analyst: free account, 1 question a day.

Sandy Ridge Wind 2, LLCJuniata Locomotive ShopUN-School House LLCCPV Rogue's Wind, LLCPatton Wind FarmSandy Ridge Wind Farm20 km
Open in the map
6 plants within 36 km, from EIA coordinates.

Key facts

Capacity
50 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
February 2012First generator online
Operator
Algonquin Power CoEIA operator ID 59050
Grid
PJMBalancing authority PJM
Price nodes
1 PJM nodeResource nodes with prices
Location
Blair County, PA40.7292, −78.2874
EIA plant ID
57285EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Sandy Ridge Wind Farm produces

Free · EIA-923

Net generation, 2025

131 GWh

131,144 MWh, final

Capacity factor, 2025

29.9%

2024: 26.6%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

105.5–155.7

GWh a year. Low 2022, high 2016

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
201292,142Not reported12 of 12
2013138,75831.7%12 of 12
2014148,96234.0%12 of 12
2015150,02434.3%12 of 12
2016155,71135.5%12 of 12
2017153,30535.0%12 of 12
2018152,26634.8%12 of 12
2019126,48728.9%12 of 12
2020143,79132.7%12 of 12
2021134,86830.8%12 of 12
2022105,46224.1%12 of 12
2023114,50026.1%12 of 12
2024116,76426.6%12 of 12
2025131,14429.9%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · PJM

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Onshore Wind Turbine50.0February 2012

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Algonquin Power Co as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Sandy Ridge Wind Farm and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Sandy Ridge Wind Farm

More plants operated by Algonquin Power Co

Questions about Sandy Ridge Wind Farm

How much power does Sandy Ridge Wind Farm produce?

Sandy Ridge Wind Farm reported 131,144 MWh (131 GWh) of net generation in 2025, a 29.9% capacity factor on 50 MW of nameplate capacity.

Where is Sandy Ridge Wind Farm?

Sandy Ridge Wind Farm is in Blair County, Pennsylvania, at 40.7292, −78.2874. It is in the PJM Interconnection, LLC balancing area (PJM).

Who operates Sandy Ridge Wind Farm?

EIA-860M for August 2026 lists Algonquin Power Co as the operator (EIA operator ID 59050). The operator is not always the owner.

When did Sandy Ridge Wind Farm start operating?

Its first generator began operating in February 2012, according to EIA-860M.

Does InfraMap have power prices for Sandy Ridge Wind Farm?

Yes. InfraMap has PJM day-ahead and real-time prices at 1 price node linked to Sandy Ridge Wind Farm, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • PJM day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Project names from the USGS U.S. Wind Turbine Database

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page