SolarOperatingAZPS

RE Bagdad Solar I LLC

Solar power plant in Yavapai County, Arizona. 14.9 MW of nameplate capacity across 1 generator, operated by Deriva Energy.

Also known as RE Bagdad Solar I · RE Bagdad Solar I, LLC · EIA plant 57790

Analyst: free account, 1 question a day.

RE Bagdad Solar I500 m
Open in the map
No other mapped plant within 60 km.

Key facts

Capacity
14.9 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
December 2011First generator online
Operator
Deriva EnergyEIA operator ID 65411
Grid
AZPSBalancing authority AZPS
Price nodes
None linkedNo verified ISO node
Location
Yavapai County, AZ34.5858, −113.1772
EIA plant ID
57790EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power RE Bagdad Solar I produces

Free · EIA-923

Net generation, 2025

30.1 GWh

30,064 MWh, final

Capacity factor, 2025

23.0%

2024: 23.9%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

26.0–34.9

GWh a year. Low 2021, high 2016

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
20112,033Not reported12 of 12
201235,97624.7%12 of 12
201334,349Not reported12 of 12
201435,36526.9%12 of 12
201534,116Not reported12 of 12
201634,86023.9%12 of 12
201734,13223.5%12 of 12
201834,34423.6%12 of 12
201932,68622.5%12 of 12
202031,453Not reported12 of 12
202126,01419.9%12 of 12
202228,78422.1%12 of 12
202331,74024.3%12 of 12
202431,26423.9%12 of 12
202530,06423.0%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Solar Photovoltaic14.9December 2011

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Deriva Energy as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query RE Bagdad Solar I LLC and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near RE Bagdad Solar I

More plants operated by Deriva Energy

Questions about RE Bagdad Solar I

How much power does RE Bagdad Solar I LLC produce?

RE Bagdad Solar I LLC reported 30,064 MWh (30.1 GWh) of net generation in 2025, a 23.0% capacity factor on 14.9 MW of nameplate capacity.

Where is RE Bagdad Solar I LLC?

RE Bagdad Solar I LLC is in Yavapai County, Arizona, at 34.5858, −113.1772. It is in the Arizona Public Service Company balancing area (AZPS).

Who operates RE Bagdad Solar I LLC?

EIA-860M for August 2026 lists Deriva Energy as the operator (EIA operator ID 65411). The operator is not always the owner.

When did RE Bagdad Solar I LLC start operating?

Its first generator began operating in December 2011, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)
  • Project names from the USGS U.S. Large-Scale Solar Photovoltaic Database

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page