SolarOperatingNEVP

Spectrum Solar PV Power Project

Solar power plant in Clark County, Nevada. 30.2 MW of nameplate capacity across 1 generator, operated by Southern Power Co.

Also known as EIA plant 58490

Analyst: free account, 1 question a day.

Nevada Cogen Associat…Nevada Cogen Assoc#1 GarnetVlyRepublic Services Renewable Energy, LLCNellis Solar PV IIIGS VGTSpectrum Solar PV Pow…10 km
Open in the map
6 plants within 17 km, from EIA coordinates.

Key facts

Capacity
30.2 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
September 2013First generator online
Operator
Southern Power CoEIA operator ID 17650
Grid
NEVPBalancing authority NEVP
Price nodes
None linkedNo verified ISO node
Location
Clark County, NV36.2300, −114.8700
EIA plant ID
58490EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Spectrum Solar PV Power Project produces

Free · EIA-923

Net generation, 2025

81.8 GWh

81,819 MWh, final

Capacity factor, 2025

30.9%

2024: 31.7%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

81.8–84.8

GWh a year. Low 2021, high 2020

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
201321,686Not reported4 of 12
201483,22931.7%12 of 12
201582,99831.6%12 of 12
201681,84931.1%12 of 12
201783,21731.7%12 of 12
201883,27331.7%12 of 12
201981,863Not reported12 of 12
202084,79832.0%12 of 12
202181,77930.9%12 of 12
202283,98331.7%12 of 12
202383,02031.4%12 of 12
202484,04631.7%12 of 12
202581,81930.9%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Solar Photovoltaic30.2September 2013

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Southern Power Co as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Spectrum Solar PV Power Project and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Spectrum Solar PV Power Project

More plants operated by Southern Power Co

Questions about Spectrum Solar PV Power Project

How much power does Spectrum Solar PV Power Project produce?

Spectrum Solar PV Power Project reported 81,819 MWh (81.8 GWh) of net generation in 2025, a 30.9% capacity factor on 30.2 MW of nameplate capacity.

Where is Spectrum Solar PV Power Project?

Spectrum Solar PV Power Project is in Clark County, Nevada, at 36.2300, −114.8700. It is in the Nevada Power Company balancing area (NEVP).

Who operates Spectrum Solar PV Power Project?

EIA-860M for August 2026 lists Southern Power Co as the operator (EIA operator ID 17650). The operator is not always the owner.

When did Spectrum Solar PV Power Project start operating?

Its first generator began operating in September 2013, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page