Key facts

Capacity
21 MWNameplate
Generators
3 operatingEIA-860M, August 2026
Operating since
April 2017First generator online
Operator
Alpaca Energy LLCEIA operator ID 58686
Grid
PJMBalancing authority PJM
Price nodes
1 PJM nodeResource nodes with prices
Location
Bradford County, PA41.6631, −76.8056
EIA plant ID
58813EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Alpaca produces

Free · EIA-923

Net generation, 2025

41.2 GWh

41,220 MWh, final

Capacity factor, 2025

22.4%

2024: 17.4%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2018 to 2025

30.8–63.0

GWh a year. Low 2020, high 2018

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
201756,937Not reported9 of 12
201862,98234.2%12 of 12
201945,09524.5%12 of 12
202030,84416.7%12 of 12
202136,38019.8%12 of 12
202246,05625.0%12 of 12
202353,65729.2%12 of 12
202432,08017.4%12 of 12
202541,22022.4%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · PJM

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Natural Gas Internal Combustion Engine7.0April 2017
2Natural Gas Internal Combustion Engine7.0April 2017
3Natural Gas Internal Combustion Engine7.0April 2017

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Alpaca Energy LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Alpaca and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Alpaca

Questions about Alpaca

How much power does Alpaca produce?

Alpaca reported 41,220 MWh (41.2 GWh) of net generation in 2025, a 22.4% capacity factor on 21 MW of nameplate capacity.

Where is Alpaca?

Alpaca is in Bradford County, Pennsylvania, at 41.6631, −76.8056. It is in the PJM Interconnection, LLC balancing area (PJM).

Who operates Alpaca?

EIA-860M for August 2026 lists Alpaca Energy LLC as the operator (EIA operator ID 58686). The operator is not always the owner.

When did Alpaca start operating?

Its first generator began operating in April 2017, according to EIA-860M.

Does InfraMap have power prices for Alpaca?

Yes. InfraMap has PJM day-ahead and real-time prices at 1 price node linked to Alpaca, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • PJM day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page