Key facts

Capacity
4.3 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
December 2018First generator online
Operator
Adapture Renewables, Inc.EIA operator ID 60496
Grid
DUKBalancing authority DUK
Price nodes
None linkedNo verified ISO node
Location
Gaston County, NC35.2290, −81.1891
EIA plant ID
60359EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Gastonia Solar Center produces

Free · EIA-923

Net generation, 2025

8.11 GWh

8,105 MWh, final

Capacity factor, 2025

21.5%

2024: 21.0%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2019 to 2025

4.4–8.3

GWh a year. Low 2019, high 2021

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018174Not reported1 of 12
20194,41111.7%12 of 12
20205,92315.7%12 of 12
20218,29122.0%12 of 12
20227,45419.8%12 of 12
20238,14821.6%12 of 12
20247,91921.0%12 of 12
20258,10521.5%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
60916Solar Photovoltaic4.3December 2018

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Adapture Renewables, Inc. as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Gastonia Solar Center and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Gastonia Solar Center

More plants operated by Adapture Renewables, Inc.

Questions about Gastonia Solar Center

How much power does Gastonia Solar Center produce?

Gastonia Solar Center reported 8,105 MWh (8.11 GWh) of net generation in 2025, a 21.5% capacity factor on 4.3 MW of nameplate capacity.

Where is Gastonia Solar Center?

Gastonia Solar Center is in Gaston County, North Carolina, at 35.2290, −81.1891. It is in the Duke Energy Carolinas balancing area (DUK).

Who operates Gastonia Solar Center?

EIA-860M for August 2026 lists Adapture Renewables, Inc. as the operator (EIA operator ID 60496). The operator is not always the owner.

When did Gastonia Solar Center start operating?

Its first generator began operating in December 2018, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page