WindOperatingMISO

Blazing Star Wind Farm 1

Wind power plant in Lincoln County, Minnesota. 200 MW of nameplate capacity across 1 generator, operated by Northern States Power Co - Minnesota.

Also known as Blazing Star 1 · EIA plant 60504

Analyst: free account, 1 question a day.

Blazing Star 2 Wind FarmBuffalo Ridge WindJack River LLCBlazing Star Wind Farm 15 km
Open in the map
6 plants within 15 km, from EIA coordinates.

Key facts

Capacity
200 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
April 2020First generator online
Operator
Northern States Power Co - MinnesotaEIA operator ID 13781
Grid
MISOBalancing authority MISO
Price nodes
1 MISO nodeResource nodes with prices
Location
Lincoln County, MN44.5441, −96.3682
EIA plant ID
60504EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Blazing Star Wind Farm 1 produces

Free · EIA-923

Net generation, 2025

873 GWh

872,782 MWh, final

Capacity factor, 2025

49.8%

2024: 46.5%

January to July 2026

501 GWh

Provisional

Range, 2021 to 2025

805.6–913.7

GWh a year. Low 2021, high 2022

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
2019Not reportedNot reported0 of 12
2020567,195Not reported9 of 12
2021805,63646.0%12 of 12
2022913,72152.2%12 of 12
2023806,81746.1%12 of 12
2024817,10846.5%12 of 12
2025872,78249.8%12 of 12
2026 (provisional, partial year)500,86049.2%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · MISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
BLZG1Onshore Wind Turbine200.0April 2020

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Northern States Power Co - Minnesota as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Blazing Star Wind Farm 1 and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Blazing Star Wind Farm 1

More plants operated by Northern States Power Co - Minnesota

Questions about Blazing Star Wind Farm 1

How much power does Blazing Star Wind Farm 1 produce?

Blazing Star Wind Farm 1 reported 872,782 MWh (873 GWh) of net generation in 2025, a 49.8% capacity factor on 200 MW of nameplate capacity. From January to July 2026 it reported 501 GWh, which is provisional.

Where is Blazing Star Wind Farm 1?

Blazing Star Wind Farm 1 is in Lincoln County, Minnesota, at 44.5441, −96.3682. It is in the Midcontinent Independent Transmission System Operator, Inc.. balancing area (MISO).

Who operates Blazing Star Wind Farm 1?

EIA-860M for August 2026 lists Northern States Power Co - Minnesota as the operator (EIA operator ID 13781). The operator is not always the owner.

When did Blazing Star Wind Farm 1 start operating?

Its first generator began operating in April 2020, according to EIA-860M.

Does InfraMap have power prices for Blazing Star Wind Farm 1?

Yes. InfraMap has MISO day-ahead and real-time prices at 1 price node linked to Blazing Star Wind Farm 1, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • MISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Project names from the USGS U.S. Wind Turbine Database

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page