HydroOperatingPSEI

Hancock Creek Hydroelectric Project

Hydro power plant in King County, Washington. 6 MW of nameplate capacity across 1 generator, operated by PUD No 1 of Snohomish County - (WA).

Also known as EIA plant 60517

Analyst: free account, 1 question a day.

Black CreekCalligan Creek Hydroelectric ProjectSnoqualmieTwin Falls HydroWeeks FallsHancock Creek Hydroel…5 km
Open in the map
6 plants within 16 km, from EIA coordinates.

Key facts

Capacity
6 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
February 2018First generator online
Operator
PUD No 1 of Snohomish County - (WA)EIA operator ID 17470
Grid
PSEIBalancing authority PSEI
Price nodes
None linkedNo verified ISO node
Location
King County, WA47.5722, −121.6897
EIA plant ID
60517EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Hancock Creek Hydroelectric Project produces

Free · EIA-923

Net generation, 2025

18.3 GWh

18,260 MWh, final

Capacity factor, 2025

34.7%

2024: 43.6%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2017 to 2025

0.0–23.0

GWh a year. Low 2017, high 2024

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
20170Not reported12 of 12
201813,048Not reported11 of 12
20199,99319.0%12 of 12
202021,62041.0%12 of 12
202119,71237.5%12 of 12
20224,2238.0%12 of 12
202316,578Not reported12 of 12
202422,99943.6%12 of 12
202518,26034.7%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
HY1Conventional Hydroelectric6.0February 2018

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists PUD No 1 of Snohomish County - (WA) as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Hancock Creek Hydroelectric Project and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Hancock Creek Hydroelectric Project

More plants operated by PUD No 1 of Snohomish County - (WA)

Questions about Hancock Creek Hydroelectric Project

How much power does Hancock Creek Hydroelectric Project produce?

Hancock Creek Hydroelectric Project reported 18,260 MWh (18.3 GWh) of net generation in 2025, a 34.7% capacity factor on 6 MW of nameplate capacity.

Where is Hancock Creek Hydroelectric Project?

Hancock Creek Hydroelectric Project is in King County, Washington, at 47.5722, −121.6897. It is in the Puget Sound Energy balancing area (PSEI).

Who operates Hancock Creek Hydroelectric Project?

EIA-860M for August 2026 lists PUD No 1 of Snohomish County - (WA) as the operator (EIA operator ID 17470). The operator is not always the owner.

When did Hancock Creek Hydroelectric Project start operating?

Its first generator began operating in February 2018, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page