Suwannee Solar Facility
Solar power plant in Suwannee County, Florida. 8.8 MW of nameplate capacity across 1 generator, operated by Duke Energy Florida, LLC.
Also known as EIA plant 60788
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 8.8 MWNameplate
- Generators
- 1 operatingEIA-860M, August 2026
- Operating since
- November 2017First generator online
- Operator
- Duke Energy Florida, LLCEIA operator ID 6455
- Grid
- FPCBalancing authority FPC
- Price nodes
- None linkedNo verified ISO node
- Location
- Suwannee County, FL30.3763, −83.1741
- EIA plant ID
- 60788EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Suwannee Solar Facility produces
Free · EIA-923Net generation, 2025
17.1 GWh
17,084 MWh, final
Capacity factor, 2025
22.2%
2024: 21.0%
January to July 2026
Not reported
Provisional. 0 of 7 months reported
Range, 2018 to 2025
14.8–18.7
GWh a year. Low 2018, high 2019
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | Not reported | Not reported | 0 of 12 |
| 2006 | Not reported | Not reported | 0 of 12 |
| 2007 | Not reported | Not reported | 0 of 12 |
| 2008 | Not reported | Not reported | 0 of 12 |
| 2009 | Not reported | Not reported | 0 of 12 |
| 2010 | Not reported | Not reported | 0 of 12 |
| 2011 | Not reported | Not reported | 0 of 12 |
| 2012 | Not reported | Not reported | 0 of 12 |
| 2013 | Not reported | Not reported | 0 of 12 |
| 2014 | Not reported | Not reported | 0 of 12 |
| 2015 | Not reported | Not reported | 0 of 12 |
| 2016 | Not reported | Not reported | 0 of 12 |
| 2017 | 1,871 | Not reported | 2 of 12 |
| 2018 | 14,767 | 19.2% | 12 of 12 |
| 2019 | 18,748 | 24.3% | 12 of 12 |
| 2020 | 18,188 | 23.5% | 12 of 12 |
| 2021 | 16,938 | 22.0% | 12 of 12 |
| 2022 | 17,310 | 22.5% | 12 of 12 |
| 2023 | 16,687 | 21.6% | 12 of 12 |
| 2024 | 16,212 | 21.0% | 12 of 12 |
| 2025 | 17,084 | 22.2% | 12 of 12 |
| 2026 (provisional, partial year) | Not reported | Not reported | 0 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free accountNo verified ISO price node is linked to this plant, or its price history could not load.
Emissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| XXXXX | Solar Photovoltaic | 8.8 | November 2017 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Duke Energy Florida, LLC as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Modeled curtailment
A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.
Expected vs reported generation
Monthly modeled expected output and physical potential next to EIA-923 reported output.
300 analyst questions a month, plus MCP
Query Suwannee Solar Facility and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Suwannee Solar Facility
More plants operated by Duke Energy Florida, LLC
Questions about Suwannee Solar Facility
How much power does Suwannee Solar Facility produce?
Suwannee Solar Facility reported 17,084 MWh (17.1 GWh) of net generation in 2025, a 22.2% capacity factor on 8.8 MW of nameplate capacity.
Where is Suwannee Solar Facility?
Suwannee Solar Facility is in Suwannee County, Florida, at 30.3763, −83.1741. It is in the Duke Energy Florida Inc balancing area (FPC).
Who operates Suwannee Solar Facility?
EIA-860M for August 2026 lists Duke Energy Florida, LLC as the operator (EIA operator ID 6455). The operator is not always the owner.
When did Suwannee Solar Facility start operating?
Its first generator began operating in November 2017, according to EIA-860M.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page