Natural gasOperatingFPC

Anclote

Natural gas power plant in Pasco County, Florida. 1,112.4 MW of nameplate capacity across 2 generators, operated by Duke Energy Florida, LLC.

Also known as Anclote Power Plant · EIA plant 8048

Analyst: free account, 1 question a day.

Lockheed Martin Solar SystemShady Hills Generating StationPasco Cnty Solid Wast…TIA SolarPinellas County Resource RecoveryAnclote20 km
Open in the map
6 plants within 41 km, from EIA coordinates.

Key facts

Capacity
1,112.4 MWNameplate
Generators
2 operatingEIA-860M, August 2026
Operating since
October 1974First generator online
Operator
Duke Energy Florida, LLCEIA operator ID 6455
Grid
FPCBalancing authority FPC
Price nodes
None linkedNo verified ISO node
Location
Pasco County, FL28.1844, −82.7886
EIA plant ID
8048EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Anclote produces

Free · EIA-923

Net generation, 2025

2.02 TWh

2,015,598 MWh, final

Capacity factor, 2025

20.7%

2024: 16.7%

January to July 2026

1.40 TWh

Provisional

Range, 2016 to 2025

1.6–3.5

TWh a year. Low 2024, high 2016

Annual net generation, TWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
20004,098,420Not reported12 of 12
20014,124,241Not reported12 of 12
20024,133,979Not reported12 of 12
20034,023,173Not reported12 of 12
20044,487,885Not reported12 of 12
20054,302,160Not reported12 of 12
20062,940,530Not reported12 of 12
20073,289,292Not reported12 of 12
20082,457,705Not reported12 of 12
20091,586,222Not reported12 of 12
20101,887,40719.4%12 of 12
20111,613,80016.6%12 of 12
20121,707,23917.5%12 of 12
20131,556,246Not reported12 of 12
20142,433,90825.0%12 of 12
20152,723,35330.4%11 of 12
20163,498,18135.8%12 of 12
20172,869,60829.4%12 of 12
20182,714,48227.9%12 of 12
20192,278,49823.4%12 of 12
20202,243,88923.0%12 of 12
20212,112,06321.7%12 of 12
20222,248,56423.1%12 of 12
20231,737,28417.8%12 of 12
20241,635,96516.7%12 of 12
20252,015,59820.7%12 of 12
2026 (provisional, partial year)1,404,70224.8%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

CO₂, 2025

1.40M

US short tons. 2024: 1.13M

SO₂, 2025

7

US short tons

NOx, 2025

1,349

US short tons

CO₂ per MWh, calculated

0.69 t

About 1,385 lb per MWh

2 of 2 EPA units reported CO₂ in 2025 (1, 2), matched to EIA plant 8048 through the EPA–EIA crosswalk. The per-MWh rate is EPA CO₂ divided by EIA-923 net generation. The two reporting boundaries can differ.

Water use

Free · EIA-923 cooling, USGS

Withdrawal, 2024

422,544

million gallons

Consumption, 2024

0

million gallons

Source

Anclote River

Surface, Brackish. Once-through

Watershed stress

Low · 0.238

USGS SUI, HUC12 Oyster Creek-Frontal Gulf of Mexico

12 of 12 cooling months report withdrawal. Saline, brackish or ocean intake; not tested. Blank volumes are unreported, not zero.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Natural Gas Steam Turbine556.2October 1974
2Natural Gas Steam Turbine556.2October 1978

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Duke Energy Florida, LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Anclote and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Anclote

More plants operated by Duke Energy Florida, LLC

Questions about Anclote

How much power does Anclote produce?

Anclote reported 2,015,598 MWh (2.02 TWh) of net generation in 2025, a 20.7% capacity factor on 1,112.4 MW of nameplate capacity. From January to July 2026 it reported 1.40 TWh, which is provisional.

Where is Anclote?

Anclote is in Pasco County, Florida, at 28.1844, −82.7886. It is in the Progress Energy Florida balancing area (FPC).

Who operates Anclote?

EIA-860M for August 2026 lists Duke Energy Florida, LLC as the operator (EIA operator ID 6455). The operator is not always the owner.

When did Anclote start operating?

Its first generator began operating in October 1974, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • EPA CAMPD annual emissions through the EPA–EIA crosswalk, 1995 to 2025
  • EIA-923 cooling water 2024 and the USGS surface water supply and use index, Water years 2010-2020 (Oct 2009 to Sep 2020), mean of monthly values
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page