WindOperatingMISO

Beaver Creek Wind

Wind power plant in Boone County, Iowa. 340 MW of nameplate capacity across 2 generators, operated by MidAmerican Energy Co.

Also known as Beaver Creek Wind Farm · Beaver Creek · EIA plant 61079

Analyst: free account, 1 question a day.

Rippey Wind FarmHardin Hilltop Wind LLCDayton (IA)Grand JunctionGowrieBeaver Creek Wind10 km
Open in the map
6 plants within 22 km, from EIA coordinates.

Key facts

Capacity
340 MWNameplate
Generators
2 operatingEIA-860M, August 2026
Operating since
December 2017First generator online
Operator
MidAmerican Energy CoEIA operator ID 12341
Grid
MISOBalancing authority MISO
Price nodes
1 MISO nodeResource nodes with prices
Location
Boone County, IA42.1070, −94.1646
EIA plant ID
61079EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Beaver Creek Wind produces

Free · EIA-923

Net generation, 2025

1.26 TWh

1,258,157 MWh, final

Capacity factor, 2025

42.2%

2024: 45.9%

January to July 2026

759 GWh

Provisional

Range, 2018 to 2025

0.6–1.5

TWh a year. Low 2018, high 2022

Annual net generation, TWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
201741,394Not reported1 of 12
2018647,98843.5%12 of 12
20191,201,80240.4%12 of 12
20201,252,62341.9%12 of 12
20211,280,86943.0%12 of 12
20221,483,76849.8%12 of 12
20231,299,75243.6%12 of 12
20241,371,48445.9%12 of 12
20251,258,15742.2%12 of 12
2026 (provisional, partial year)758,61143.9%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · MISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Onshore Wind Turbine170.0December 2017
GT1Onshore Wind Turbine170.0October 2018

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists MidAmerican Energy Co as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Beaver Creek Wind and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Beaver Creek Wind

More plants operated by MidAmerican Energy Co

Questions about Beaver Creek Wind

How much power does Beaver Creek Wind produce?

Beaver Creek Wind reported 1,258,157 MWh (1.26 TWh) of net generation in 2025, a 42.2% capacity factor on 340 MW of nameplate capacity. From January to July 2026 it reported 759 GWh, which is provisional.

Where is Beaver Creek Wind?

Beaver Creek Wind is in Boone County, Iowa, at 42.1070, −94.1646. It is in the Midcontinent Independent Transmission System Operator, Inc.. balancing area (MISO).

Who operates Beaver Creek Wind?

EIA-860M for August 2026 lists MidAmerican Energy Co as the operator (EIA operator ID 12341). The operator is not always the owner.

When did Beaver Creek Wind start operating?

Its first generator began operating in December 2017, according to EIA-860M.

Does InfraMap have power prices for Beaver Creek Wind?

Yes. InfraMap has MISO day-ahead and real-time prices at 1 price node linked to Beaver Creek Wind, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • MISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)
  • Project names from the USGS U.S. Wind Turbine Database

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page