Lindstrom Solar CSG

Solar power plant in Chisago County, Minnesota. 3 MW of nameplate capacity across 3 generators, operated by Geronimo Power.

Also known as Lindstrom Solar (CSG) · EIA plant 61382

Analyst: free account, 1 question a day.

Olinda Trail SolarNautilus Lindstrom Solar (CSG)Gemini Community SolarScandia Community Solar GardenEichtens Community SolarArgo Navis Community SolarLindstrom Solar CSG2 km
Open in the map
6 plants within 7.4 km, from EIA coordinates.

Key facts

Capacity
3 MWNameplate
Generators
3 operatingEIA-860M, August 2026
Operating since
April 2018First generator online
Operator
Geronimo PowerEIA operator ID 62759
Grid
MISOBalancing authority MISO
Price nodes
None linkedNo verified ISO node
Location
Chisago County, MN45.3199, −92.7966
EIA plant ID
61382EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Lindstrom Solar CSG produces

Free · EIA-923

Net generation, 2025

5.10 GWh

5,098 MWh, final

Capacity factor, 2025

19.4%

2024: 20.1%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2019 to 2025

5.0–5.7

GWh a year. Low 2019, high 2021

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
20183,626Not reported9 of 12
20194,99019.0%12 of 12
20205,47420.8%12 of 12
20215,68321.6%12 of 12
20225,23819.9%12 of 12
20235,30120.2%12 of 12
20245,29820.1%12 of 12
20255,09819.4%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
LIND1Solar Photovoltaic1.0April 2018
LIND2Solar Photovoltaic1.0April 2018
LIND3Solar Photovoltaic1.0April 2018

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Geronimo Power as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Lindstrom Solar CSG and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Lindstrom Solar CSG

More plants operated by Geronimo Power

Questions about Lindstrom Solar CSG

How much power does Lindstrom Solar CSG produce?

Lindstrom Solar CSG reported 5,098 MWh (5.10 GWh) of net generation in 2025, a 19.4% capacity factor on 3 MW of nameplate capacity.

Where is Lindstrom Solar CSG?

Lindstrom Solar CSG is in Chisago County, Minnesota, at 45.3199, −92.7966. It is in the Midcontinent Independent Transmission System Operator, Inc.. balancing area (MISO).

Who operates Lindstrom Solar CSG?

EIA-860M for August 2026 lists Geronimo Power as the operator (EIA operator ID 62759). The operator is not always the owner.

When did Lindstrom Solar CSG start operating?

Its first generator began operating in April 2018, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • Project names from the USGS U.S. Large-Scale Solar Photovoltaic Database

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page