WindOperatingNYISO

Arkwright Summit Wind Farm LLC

Wind power plant in Chautauqua County, New York. 78.4 MW of nameplate capacity across 1 generator, operated by Arkwright Summit Wind Farm LLC.

Also known as Arkwright Summit Wind Farm · Arkwright Summit · EIA plant 61673

Analyst: free account, 1 question a day.

Rak 1NY Fredonia 9824 Route 60 SolarFredonia Solar LLCCassadaga Wind FarmRivard 2Arkwright Summit Wind Farm5 km
Open in the map
6 plants within 10 km, from EIA coordinates.

Key facts

Capacity
78.4 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
August 2018First generator online
Operator
Arkwright Summit Wind Farm LLCEIA operator ID 58261
Grid
NYISOBalancing authority NYIS
Price nodes
1 NYISO nodeResource nodes with prices
Location
Chautauqua County, NY42.4149, −79.2427
EIA plant ID
61673EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Arkwright Summit Wind Farm produces

Free · EIA-923

Net generation, 2025

262 GWh

262,335 MWh, final

Capacity factor, 2025

38.2%

2024: 33.4%

January to July 2026

139 GWh

Provisional

Range, 2019 to 2025

224.1–262.3

GWh a year. Low 2023, high 2025

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
201886,25236.9%4 of 12
2019256,39736.7%12 of 12
2020255,805Not reported12 of 12
2021233,51934.0%12 of 12
2022260,56937.9%12 of 12
2023224,13732.6%12 of 12
2024229,81933.4%12 of 12
2025262,33538.2%12 of 12
2026 (provisional, partial year)139,02834.9%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · NYISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
WTOnshore Wind Turbine78.4August 2018

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Arkwright Summit Wind Farm LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Arkwright Summit Wind Farm LLC and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Arkwright Summit Wind Farm

Questions about Arkwright Summit Wind Farm

How much power does Arkwright Summit Wind Farm LLC produce?

Arkwright Summit Wind Farm LLC reported 262,335 MWh (262 GWh) of net generation in 2025, a 38.2% capacity factor on 78.4 MW of nameplate capacity. From January to July 2026 it reported 139 GWh, which is provisional.

Where is Arkwright Summit Wind Farm LLC?

Arkwright Summit Wind Farm LLC is in Chautauqua County, New York, at 42.4149, −79.2427. It is in the New York Independent System Operator balancing area (NYIS).

Who operates Arkwright Summit Wind Farm LLC?

EIA-860M for August 2026 lists Arkwright Summit Wind Farm LLC as the operator (EIA operator ID 58261). The operator is not always the owner.

When did Arkwright Summit Wind Farm LLC start operating?

Its first generator began operating in August 2018, according to EIA-860M.

Does InfraMap have power prices for Arkwright Summit Wind Farm LLC?

Yes. InfraMap has NYISO day-ahead and real-time prices at 1 price node linked to Arkwright Summit Wind Farm LLC, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • NYISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)
  • Project names from the USGS U.S. Wind Turbine Database

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page