SolarBattery storageOperatingFPL

Sunshine Gateway Solar Energy Center

Solar and battery storage project in Columbia County, Florida. 104.5 MW of nameplate capacity across 2 generators, operated by Florida Power & Light Co.

Also known as EIA plant 61763

This project groups Sunshine Gateway Solar Energy Center (EIA 61763). EIA reports them as separate plants.

Analyst: free account, 1 question a day.

Echo River SolarSwift Creek Chemical ComplexPrice CreekHildreth Solar Power PlantFalmouth Renewable Energy CenterSunshine Gateway Solar20 km
Open in the map
6 plants within 39 km, from EIA coordinates.

Key facts

Capacity
104.5 MWSolar 74.5 · Battery storage 30.0
Generators
2 operatingEIA-860M, August 2026
Operating since
January 2019First generator online
Operator
Florida Power & Light CoEIA operator ID 6452
Grid
FPLBalancing authority FPL
Price nodes
None linkedNo verified ISO node
Location
Columbia County, FL30.2900, −82.7500
EIA plant ID
61763EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Sunshine Gateway Solar produces

Free · EIA-923

Net generation, 2025

135 GWh

134,854 MWh, final

Capacity factor, 2025

21.0%

2024: 20.4%

January to July 2026

79.5 GWh

Provisional

Range, 2019 to 2025

130.3–152.3

GWh a year. Low 2024, high 2020

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
2019145,71923.2%12 of 12
2020152,32623.3%12 of 12
20218,770Not reported1 of 12
2022147,91323.1%12 of 12
2023137,84521.5%12 of 12
2024130,30020.4%12 of 12
2025134,85421.0%12 of 12
2026 (provisional, partial year)79,47521.3%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Solar Photovoltaic74.5January 2019
2Batteries30.0December 2021

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Florida Power & Light Co as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Sunshine Gateway Solar Energy Center and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Sunshine Gateway Solar

More plants operated by Florida Power & Light Co

Questions about Sunshine Gateway Solar

How much power does Sunshine Gateway Solar Energy Center produce?

Sunshine Gateway Solar Energy Center reported 134,854 MWh (135 GWh) of net generation in 2025, a 21.0% capacity factor on 104.5 MW of nameplate capacity. From January to July 2026 it reported 79.5 GWh, which is provisional.

Where is Sunshine Gateway Solar Energy Center?

Sunshine Gateway Solar Energy Center is in Columbia County, Florida, at 30.2900, −82.7500. It is in the Florida Power & Light Company balancing area (FPL).

Who operates Sunshine Gateway Solar Energy Center?

EIA-860M for August 2026 lists Florida Power & Light Co as the operator (EIA operator ID 6452). The operator is not always the owner.

Is Sunshine Gateway Solar Energy Center a solar or a battery storage plant?

Both. Solar capacity totals 74.5 MW and battery storage capacity totals 30 MW.

When did Sunshine Gateway Solar Energy Center start operating?

Its first generator began operating in January 2019, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page