Lumina II Solar Project

Solar and battery storage project in Scurry County, Texas. 486.6 MW of nameplate capacity across 2 generators, operated by Intersect USA, LLC.

Also known as EIA plant 65644

This project groups Lumina II Solar Project (EIA 65644). EIA reports them as separate plants.

Analyst: free account, 1 question a day.

Coyote Wind LLCCross Trails Energy Storage ProjectScurry County Wind IIAmadeus Wind FarmLumina Solar ProjectLumina II Solar Project10 km
Open in the map
6 plants within 22 km, from EIA coordinates.

Key facts

Capacity
486.6 MWSolar 326.6 · Battery storage 160.0
Generators
2 operatingEIA-860M, August 2026
Operating since
January 2024First generator online
Operator
Intersect USA, LLCEIA operator ID 67582
Grid
ERCOTBalancing authority ERCO
Price nodes
1 ERCOT nodeResource nodes with prices
Location
Scurry County, TX32.8835, −100.7464
EIA plant ID
65644EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Lumina II Solar Project produces

Free · EIA-923

Net generation, 2025

135 GWh

135,049 MWh, final. 3 of 12 months reported

Capacity factor, 2025

Not reported

2024: 24.9%

January to July 2026

429 GWh

Provisional

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
2019Not reportedNot reported0 of 12
2020Not reportedNot reported0 of 12
2021Not reportedNot reported0 of 12
2022Not reportedNot reported0 of 12
2023Not reportedNot reported0 of 12
2024693,79624.9%12 of 12
2025135,049Not reported3 of 12
2026 (provisional, partial year)429,46526.5%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · ERCOT

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
LU2BABatteries160.0October 2025
LUMIISolar Photovoltaic326.6January 2024

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Intersect USA, LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Lumina II Solar Project and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Lumina II Solar Project

More plants operated by Intersect USA, LLC

Questions about Lumina II Solar Project

How much power does Lumina II Solar Project produce?

Lumina II Solar Project reported 135,049 MWh (135 GWh) of net generation in 2025. From January to July 2026 it reported 429 GWh, which is provisional. 3 of 12 months were reported for 2025.

Where is Lumina II Solar Project?

Lumina II Solar Project is in Scurry County, Texas, at 32.8835, −100.7464. It is in the Electric Reliability Council of Texas, Inc. balancing area (ERCO).

Who operates Lumina II Solar Project?

EIA-860M for August 2026 lists Intersect USA, LLC as the operator (EIA operator ID 67582). The operator is not always the owner.

Is Lumina II Solar Project a solar or a battery storage plant?

Both. Solar capacity totals 326.6 MW and battery storage capacity totals 160 MW.

When did Lumina II Solar Project start operating?

Its first generator began operating in January 2024, according to EIA-860M.

Does InfraMap have power prices for Lumina II Solar Project?

Yes. InfraMap has ERCOT day-ahead and real-time prices at 1 price node linked to Lumina II Solar Project, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • ERCOT day-ahead and real-time prices; node and hub assignments as of 2026-10-05

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page