Battery storageOperatingERCOT

Revolution

Battery storage project in Crane County, Texas. 150 MW of nameplate capacity across 1 generator, operated by Crane 2 BESS, LLC.

Also known as EIA plant 66170

Analyst: free account, 1 question a day.

Upton County BESSUpton County SolarCrane Solar ProjectCrossett Power Manage…Revolution2 km
Open in the map
5 plants within 4.7 km, from EIA coordinates.

Key facts

Capacity
150 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
December 2023First generator online
Operator
Crane 2 BESS, LLCEIA operator ID 65313
Grid
ERCOTBalancing authority ERCO
Price nodes
1 ERCOT nodeResource nodes with prices
Location
Crane County, TX31.2335, −102.3085
EIA plant ID
66170EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Revolution produces

Free · EIA-923

Net generation, 2025

−13.9 GWh

−13,902 MWh, final

Battery discharge, 2025

83.4 GWh

Charge 97.3 GWh

January to July 2026

−12.1 GWh

Provisional

Range, 2024 to 2025

−13.9–−13.1

GWh a year. Low 2025, high 2024

Annual net generation, GWh
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
2019Not reportedNot reported0 of 12
2020Not reportedNot reported0 of 12
2021Not reportedNot reported0 of 12
2022Not reportedNot reported0 of 12
2023Not reportedNot reported0 of 12
2024−13,129Not reported12 of 12
2025−13,902Not reported12 of 12
2026 (provisional, partial year)−12,071Not reported7 of 7

* 2026 covers January to July and is provisional. Battery plants can report negative net generation, when charging uses more energy than they discharge.

Power prices and basis

Free account · ERCOT

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Batteries150.0December 2023

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Crane 2 BESS, LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Revolution and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Revolution

Questions about Revolution

How much power does Revolution produce?

Revolution reported −13,902 MWh (−13.9 GWh) of net generation in 2025. From January to July 2026 it reported −12.1 GWh, which is provisional.

Where is Revolution?

Revolution is in Crane County, Texas, at 31.2335, −102.3085. It is in the Electric Reliability Council of Texas, Inc. balancing area (ERCO).

Who operates Revolution?

EIA-860M for August 2026 lists Crane 2 BESS, LLC as the operator (EIA operator ID 65313). The operator is not always the owner.

When did Revolution start operating?

Its first generator began operating in December 2023, according to EIA-860M.

Does InfraMap have power prices for Revolution?

Yes. InfraMap has ERCOT day-ahead and real-time prices at 1 price node linked to Revolution, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • ERCOT day-ahead and real-time prices; node and hub assignments as of 2026-10-05

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page