SolarBattery storageOperatingSOCO

401 South

Solar and battery storage project in Berkshire County, Massachusetts. 1.5 MW of nameplate capacity across 2 generators, operated by Madison Energy Investments LLC.

Also known as EIA plant 67241

This project groups 401 South (EIA 67241). EIA reports them as separate plants.

Analyst: free account, 1 question a day.

Partridge SolarSilver Lake Solar Photovoltaic Facility401 South2 km
Open in the map
6 plants within 5.4 km, from EIA coordinates.

Key facts

Capacity
1.5 MWSolar 0.5 · Battery storage 1.0
Generators
2 operatingEIA-860M, August 2026
Operating since
December 2023First generator online
Operator
Madison Energy Investments LLCEIA operator ID 65043
Grid
SOCOBalancing authority SOCO
Price nodes
None linkedNo verified ISO node
Location
Berkshire County, MA42.4640, −73.1840
EIA plant ID
67241EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power 401 South produces

Free · EIA-923

Net generation, 2025

945 MWh

945 MWh, final

Capacity factor, 2025

21.6%

2024: 9.2%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2023 to 2025

0.0–945.0

MWh a year. Low 2023, high 2025

Annual net generation, MWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
2019Not reportedNot reported0 of 12
2020Not reportedNot reported0 of 12
2021Not reportedNot reported0 of 12
2022Not reportedNot reported0 of 12
20230Not reported12 of 12
20244039.2%12 of 12
202594521.6%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
4SPV1Solar Photovoltaic0.5December 2023
401SBBatteries1.0December 2023

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Madison Energy Investments LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query 401 South and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near 401 South

More plants operated by Madison Energy Investments LLC

Questions about 401 South

How much power does 401 South produce?

401 South reported 945 MWh (945 MWh) of net generation in 2025, a 21.6% capacity factor on 1.5 MW of nameplate capacity.

Where is 401 South?

401 South is in Berkshire County, Massachusetts, at 42.4640, −73.1840. It is in the Southern Company Services, Inc. - Trans balancing area (SOCO).

Who operates 401 South?

EIA-860M for August 2026 lists Madison Energy Investments LLC as the operator (EIA operator ID 65043). The operator is not always the owner.

Is 401 South a solar or a battery storage plant?

Both. Solar capacity totals 0.5 MW and battery storage capacity totals 1 MW.

When did 401 South start operating?

Its first generator began operating in December 2023, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page