Battery storageOperatingERCOT

Project Lynx

Battery storage project in Nueces County, Texas. 125 MW of nameplate capacity across 1 generator, operated by Project Lynx - Giga Texas Energy.

Also known as EIA plant 69286

Analyst: free account, 1 question a day.

Corpus ChristiRegis HearnPatriot Wind FarmTicona Polymers IncCorpus RefineryProject Lynx10 km
Open in the map
6 plants within 23 km, from EIA coordinates.

Key facts

Capacity
125 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
August 2026First generator online
Operator
Project Lynx - Giga Texas EnergyEIA operator ID 67382
Grid
ERCOTBalancing authority ERCO
Price nodes
1 ERCOT nodeResource nodes with prices
Location
Nueces County, TX27.7292, −97.7331
EIA plant ID
69286EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Project Lynx produces

Free · EIA-923

EIA-923 has no net generation reported for this plant.

Power prices and basis

Free account · ERCOT

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
LYNXBatteries125.0August 2026

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Project Lynx - Giga Texas Energy as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Project Lynx and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Project Lynx

Questions about Project Lynx

Where is Project Lynx?

Project Lynx is in Nueces County, Texas, at 27.7292, −97.7331. It is in the Electric Reliability Council of Texas, Inc. balancing area (ERCO).

Who operates Project Lynx?

EIA-860M for August 2026 lists Project Lynx - Giga Texas Energy as the operator (EIA operator ID 67382). The operator is not always the owner.

When did Project Lynx start operating?

Its first generator began operating in August 2026, according to EIA-860M.

Does InfraMap have power prices for Project Lynx?

Yes. InfraMap has ERCOT day-ahead and real-time prices at 1 price node linked to Project Lynx, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • ERCOT day-ahead and real-time prices; node and hub assignments as of 2026-10-05

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page