Natural gasOperatingSOCO

McIntosh (AL)

Natural gas power plant in Washington County, Alabama. 676 MW of nameplate capacity across 5 generators, operated by PowerSouth Energy Cooperative.

Also known as McIntosh Power Plant · EIA plant 7063

Analyst: free account, 1 question a day.

BarryLowman Energy CenterWalker Springs IIWalker Springs IMcIntosh (AL)20 km
Open in the map
6 plants within 37 km, from EIA coordinates.

Key facts

Capacity
676 MWNameplate
Generators
5 operatingEIA-860M, August 2026
Operating since
June 1991First generator online
Operator
PowerSouth Energy CooperativeEIA operator ID 189
Grid
SOCOBalancing authority SOCO
Price nodes
None linkedNo verified ISO node
Location
Washington County, AL31.2546, −88.0299
EIA plant ID
7063EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power McIntosh (AL) produces

Free · EIA-923

Net generation, 2025

315 GWh

315,250 MWh, final

Capacity factor, 2025

6.4%

2024: 5.2%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

138.3–792.9

GWh a year. Low 2017, high 2022

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000216,779Not reported12 of 12
200193,043Not reported12 of 12
200280,968Not reported12 of 12
200370,597Not reported12 of 12
200466,621Not reported12 of 12
200558,951Not reported12 of 12
200621,587Not reported12 of 12
200723,862Not reported12 of 12
200857,617Not reported12 of 12
200932,639Not reported12 of 12
2010134,764Not reported12 of 12
2011242,4784.1%12 of 12
2012173,9192.9%12 of 12
201352,053Not reported12 of 12
2014123,5442.5%12 of 12
2015270,0555.4%12 of 12
2016308,8716.2%12 of 12
2017138,3272.8%12 of 12
2018432,5238.7%12 of 12
2019661,23213.3%12 of 12
2020369,9747.4%12 of 12
2021572,94211.6%12 of 12
2022792,90816.0%12 of 12
2023745,69115.0%12 of 12
2024256,3765.2%12 of 12
2025315,2506.4%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

CO₂, 2025

225,751

US short tons. 2024: 179,084

SO₂, 2025

1

US short tons

NOx, 2025

94

US short tons

CO₂ per MWh, calculated

0.72 t

About 1,432 lb per MWh

4 of 4 EPA units reported CO₂ in 2025 (**2, **3, **4, **5), matched to EIA plant 7063 through the EPA–EIA crosswalk. The per-MWh rate is EPA CO₂ divided by EIA-923 net generation. The two reporting boundaries can differ.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Natural Gas with Compressed Air Storage110.0June 1991
2Natural Gas Fired Combustion Turbine113.0June 1998
3Natural Gas Fired Combustion Turbine113.0June 1998
4Natural Gas Fired Combustion Turbine170.0December 2010
5Natural Gas Fired Combustion Turbine170.0December 2010

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists PowerSouth Energy Cooperative as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query McIntosh (AL) and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near McIntosh (AL)

More plants operated by PowerSouth Energy Cooperative

Questions about McIntosh (AL)

How much power does McIntosh (AL) produce?

McIntosh (AL) reported 315,250 MWh (315 GWh) of net generation in 2025, a 6.4% capacity factor on 676 MW of nameplate capacity.

Where is McIntosh (AL)?

McIntosh (AL) is in Washington County, Alabama, at 31.2546, −88.0299. It is in the Southern Company Services, Inc. - Trans balancing area (SOCO).

Who operates McIntosh (AL)?

EIA-860M for August 2026 lists PowerSouth Energy Cooperative as the operator (EIA operator ID 189). The operator is not always the owner.

When did McIntosh (AL) start operating?

Its first generator began operating in June 1991, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • EPA CAMPD annual emissions through the EPA–EIA crosswalk, 1995 to 2025
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page