CoalOperatingSC

Cross

Coal power plant in Berkeley County, South Carolina. 2,451.5 MW of nameplate capacity across 4 generators, operated by South Carolina Public Service Authority.

Also known as Cross Generating Station · EIA plant 130

Analyst: free account, 1 question a day.

SpillwaySt StephenJefferiesOmtanke SolarBloom SolarDorchester BiomassCross20 km
Open in the map
6 plants within 35 km, from EIA coordinates.

Key facts

Capacity
2,451.5 MWNameplate
Generators
4 operatingEIA-860M, August 2026
Operating since
May 1984First generator online
Operator
South Carolina Public Service AuthorityEIA operator ID 17543
Grid
SCBalancing authority SC
Price nodes
None linkedNo verified ISO node
Location
Berkeley County, SC33.3715, −80.1132
EIA plant ID
130EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Cross produces

Free · EIA-923

Net generation, 2025

8.77 TWh

8,773,860 MWh, final

Capacity factor, 2025

40.9%

2024: Not reported

January to July 2026

4.82 TWh

Provisional

Range, 2015 to 2025

6.2–10.1

TWh a year. Low 2020, high 2016

Annual net generation, TWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
20008,612,473Not reported12 of 12
20018,385,434Not reported12 of 12
20028,126,251Not reported12 of 12
20038,214,027Not reported12 of 12
20048,618,031Not reported12 of 12
20058,148,937Not reported12 of 12
20068,576,427Not reported12 of 12
200712,338,184Not reported12 of 12
200813,621,885Not reported12 of 12
200914,619,848Not reported12 of 12
201014,660,23170.0%12 of 12
201114,331,66868.5%12 of 12
201213,068,75762.2%12 of 12
201312,659,91660.5%12 of 12
20143,885,16656.4%4 of 12
20158,921,96442.6%12 of 12
201610,137,161Not reported12 of 12
20178,378,40140.0%12 of 12
20189,544,59645.6%12 of 12
20198,375,41140.0%12 of 12
20206,226,17529.7%12 of 12
20217,356,68835.1%12 of 12
20227,626,134Not reported12 of 12
20238,449,23440.4%12 of 12
20248,534,996Not reported12 of 12
20258,773,86040.9%12 of 12
2026 (provisional, partial year)4,821,22738.7%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

CO₂, 2025

9.91M

US short tons. 2024: 9.53M

SO₂, 2025

5,691

US short tons

NOx, 2025

3,517

US short tons

CO₂ per MWh, calculated

1.13 t

About 2,259 lb per MWh

4 of 4 EPA units reported CO₂ in 2025 (1, 2, 3, 4), matched to EIA plant 130 through the EPA–EIA crosswalk. The per-MWh rate is EPA CO₂ divided by EIA-923 net generation. The two reporting boundaries can differ.

Water use

Free · EIA-923 cooling, USGS

Withdrawal, 2024

5,071

million gallons

Consumption, 2024

4,918

million gallons

Source

Diversion Canal

Surface, Fresh. Induced-draft tower

Watershed stress

High · 0.635

USGS SUI, HUC12 Lake Moultrie

43 of 48 cooling months report withdrawal. SUI of the HUC12 containing the plant. Blank volumes are unreported, not zero.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Conventional Steam Coal591.4May 1995
2Conventional Steam Coal556.1May 1984
3Conventional Steam Coal652.0January 2007
4Conventional Steam Coal652.0October 2008

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists South Carolina Public Service Authority as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Cross and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Cross

More plants operated by South Carolina Public Service Authority

Questions about Cross

How much power does Cross produce?

Cross reported 8,773,860 MWh (8.77 TWh) of net generation in 2025, a 40.9% capacity factor on 2,451.5 MW of nameplate capacity. From January to July 2026 it reported 4.82 TWh, which is provisional.

Where is Cross?

Cross is in Berkeley County, South Carolina, at 33.3715, −80.1132. It is in the South Carolina Public Service Authority balancing area (SC).

Who operates Cross?

EIA-860M for August 2026 lists South Carolina Public Service Authority as the operator (EIA operator ID 17543). The operator is not always the owner.

When did Cross start operating?

Its first generator began operating in May 1984, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • EPA CAMPD annual emissions through the EPA–EIA crosswalk, 1995 to 2025
  • EIA-923 cooling water 2024 and the USGS surface water supply and use index, Water years 2010-2020 (Oct 2009 to Sep 2020), mean of monthly values
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page