Key facts

Capacity
25.5 MWNameplate
Generators
3 operatingEIA-860M, August 2026
Operating since
February 1925First generator online
Operator
Duke Energy Carolinas, LLCEIA operator ID 5416
Grid
DUKBalancing authority DUK
Price nodes
None linkedNo verified ISO node
Location
Caldwell County, NC35.7742, −81.4378
EIA plant ID
2730EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Rhodhiss produces

Free · EIA-923

Net generation, 2025

55.9 GWh

55,894 MWh, final

Capacity factor, 2025

25.0%

2024: 31.2%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

55.9–119.3

GWh a year. Low 2025, high 2018

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
200036,242Not reported12 of 12
200131,127Not reported12 of 12
200235,843Not reported12 of 12
200396,372Not reported12 of 12
200473,805Not reported12 of 12
200580,999Not reported12 of 12
200653,582Not reported12 of 12
200742,499Not reported12 of 12
200833,993Not reported12 of 12
200967,701Not reported12 of 12
201062,16427.8%12 of 12
201147,44721.2%12 of 12
201246,47620.7%12 of 12
201396,62043.3%12 of 12
201462,36027.9%12 of 12
201571,07731.8%12 of 12
201658,22126.0%12 of 12
201761,73827.6%12 of 12
2018119,29753.4%12 of 12
201995,86342.9%12 of 12
2020119,03453.1%12 of 12
202173,91933.1%12 of 12
202260,79027.2%12 of 12
202358,64126.3%12 of 12
202469,81831.2%12 of 12
202555,89425.0%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Conventional Hydroelectric8.5February 1925
2Conventional Hydroelectric8.5February 1925
3Conventional Hydroelectric8.5February 1925

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Duke Energy Carolinas, LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Rhodhiss and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Rhodhiss

More plants operated by Duke Energy Carolinas, LLC

Questions about Rhodhiss

How much power does Rhodhiss produce?

Rhodhiss reported 55,894 MWh (55.9 GWh) of net generation in 2025, a 25.0% capacity factor on 25.5 MW of nameplate capacity.

Where is Rhodhiss?

Rhodhiss is in Caldwell County, North Carolina, at 35.7742, −81.4378. It is in the Duke Energy Carolinas balancing area (DUK).

Who operates Rhodhiss?

EIA-860M for August 2026 lists Duke Energy Carolinas, LLC as the operator (EIA operator ID 5416). The operator is not always the owner.

When did Rhodhiss start operating?

Its first generator began operating in February 1925, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page