Hydro power plant in Sevier County, Tennessee. 150.8 MW of nameplate capacity across 4 generators, operated by Tennessee Valley Authority.

Also known as Douglas Dam Powerhouse · EIA plant 3400

Analyst: free account, 1 question a day.

Cherokee DamSR White Pine, LLCSR Maryville EastChestnut Ridge Gas RecoveryDouglas Dam25 km
Open in the map
6 plants within 48 km, from EIA coordinates.

Key facts

Capacity
150.8 MWNameplate
Generators
4 operatingEIA-860M, August 2026
Operating since
March 1943First generator online
Operator
Tennessee Valley AuthorityEIA operator ID 18642
Grid
TVABalancing authority TVA
Price nodes
None linkedNo verified ISO node
Location
Sevier County, TN35.9623, −83.5393
EIA plant ID
3400EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Douglas Dam produces

Free · EIA-923

Net generation, 2025

341 GWh

341,251 MWh, final

Capacity factor, 2025

25.8%

2024: 33.7%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

317.6–765.5

GWh a year. Low 2016, high 2020

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000277,511Not reported12 of 12
2001260,658Not reported12 of 12
2002265,932Not reported12 of 12
2003526,518Not reported12 of 12
2004498,017Not reported12 of 12
2005420,648Not reported12 of 12
2006343,297Not reported12 of 12
2007174,213Not reported12 of 12
2008191,097Not reported12 of 12
2009441,437Not reported12 of 12
2010348,01926.3%12 of 12
2011407,00130.8%12 of 12
2012349,79626.4%12 of 12
2013718,30454.4%12 of 12
2014334,44525.3%12 of 12
2015373,01528.2%12 of 12
2016317,58324.0%12 of 12
2017381,35428.9%12 of 12
2018573,15843.4%12 of 12
2019581,80844.0%12 of 12
2020765,46657.8%12 of 12
2021555,82342.1%12 of 12
2022395,43229.9%12 of 12
2023364,85427.6%12 of 12
2024446,39733.7%12 of 12
2025341,25125.8%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Conventional Hydroelectric36.5January 1944
2Conventional Hydroelectric41.4May 1949
3Conventional Hydroelectric31.5March 1943
4Conventional Hydroelectric41.4August 1954

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Tennessee Valley Authority as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Douglas Dam and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Douglas Dam

More plants operated by Tennessee Valley Authority

Questions about Douglas Dam

How much power does Douglas Dam produce?

Douglas Dam reported 341,251 MWh (341 GWh) of net generation in 2025, a 25.8% capacity factor on 150.8 MW of nameplate capacity.

Where is Douglas Dam?

Douglas Dam is in Sevier County, Tennessee, at 35.9623, −83.5393. It is in the Tennessee Valley Authority balancing area (TVA).

Who operates Douglas Dam?

EIA-860M for August 2026 lists Tennessee Valley Authority as the operator (EIA operator ID 18642). The operator is not always the owner.

When did Douglas Dam start operating?

Its first generator began operating in March 1943, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page