Natural gasOperatingPACE

Bountiful City

Natural gas power plant in Davis County, Utah. 30.4 MW of nameplate capacity across 3 generators, operated by City of Bountiful - (UT).

Also known as Bountiful City Power Plant · EIA plant 3665

Analyst: free account, 1 question a day.

Tesoro SLC Cogeneration PlantGadsbyHTW Plant 303 COGENSalt Lake Energy SystemsBountiful City10 km
Open in the map
6 plants within 20 km, from EIA coordinates.

Key facts

Capacity
30.4 MWNameplate
Generators
3 operatingEIA-860M, August 2026
Operating since
July 2001First generator online
Operator
City of Bountiful - (UT)EIA operator ID 2010
Grid
PACEBalancing authority PACE
Price nodes
None linkedNo verified ISO node
Location
Davis County, UT40.8869, −111.8853
EIA plant ID
3665EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Bountiful City produces

Free · EIA-923

Net generation, 2025

31.3 GWh

31,268 MWh, final

Capacity factor, 2025

11.7%

2024: 10.6%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

13.2–32.0

GWh a year. Low 2015, high 2022

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
20000Not reported12 of 12
200125,380Not reported12 of 12
200217,177Not reported12 of 12
200313,411Not reported12 of 12
20045,974Not reported12 of 12
20054,675Not reported12 of 12
20064,118Not reported12 of 12
200711,458Not reported12 of 12
20087,028Not reported12 of 12
20099,831Not reported12 of 12
20106,6123.9%12 of 12
2011206Not reported12 of 12
201220,005Not reported12 of 12
201336,13811.0%12 of 12
2014Not reportedNot reported0 of 12
201513,1855.0%12 of 12
201614,0815.3%12 of 12
201719,7837.4%12 of 12
201820,5137.7%12 of 12
201916,1306.1%12 of 12
202018,0126.7%12 of 12
202130,31311.4%12 of 12
202231,97612.0%12 of 12
202321,4348.0%12 of 12
202428,38510.6%12 of 12
202531,26811.7%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1ANatural Gas Fired Combustion Turbine5.2July 2001
2ANatural Gas Fired Combustion Turbine12.6June 2012
3ANatural Gas Fired Combustion Turbine12.6June 2012

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists City of Bountiful - (UT) as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Bountiful City and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Bountiful City

More plants operated by City of Bountiful - (UT)

Questions about Bountiful City

How much power does Bountiful City produce?

Bountiful City reported 31,268 MWh (31.3 GWh) of net generation in 2025, a 11.7% capacity factor on 30.4 MW of nameplate capacity.

Where is Bountiful City?

Bountiful City is in Davis County, Utah, at 40.8869, −111.8853. It is in the PacifiCorp - East balancing area (PACE).

Who operates Bountiful City?

EIA-860M for August 2026 lists City of Bountiful - (UT) as the operator (EIA operator ID 2010). The operator is not always the owner.

When did Bountiful City start operating?

Its first generator began operating in July 2001, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page