NuclearOperatingPJM

Surry

Nuclear power plant in Surry County, Virginia. 1,695 MW of nameplate capacity across 2 generators, operated by Virginia Electric & Power Co.

Also known as Surry Nuclear Power Plant · EIA plant 3806

Analyst: free account, 1 question a day.

Cavalier SolarCavalier Solar A2Colonial Trail WestSpring Grove ISurry10 km
Open in the map
6 plants within 20 km, from EIA coordinates.

Key facts

Capacity
1,695 MWNameplate
Generators
2 operatingEIA-860M, August 2026
Operating since
December 1972First generator online
Operator
Virginia Electric & Power CoEIA operator ID 19876
Grid
PJMBalancing authority PJM
Price nodes
2 PJM nodesResource nodes with prices
Location
Surry County, VA37.1661, −76.6986
EIA plant ID
3806EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Surry produces

Free · EIA-923

Net generation, 2025

13.2 TWh

13,218,141 MWh, final

Capacity factor, 2025

89.0%

2024: 86.8%

January to July 2026

7.48 TWh

Provisional

Range, 2015 to 2025

11.8–14.6

TWh a year. Low 2015, high 2016

Annual net generation, TWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
200013,087,875Not reported12 of 12
200112,662,376Not reported12 of 12
200213,672,127Not reported12 of 12
200311,031,898Not reported12 of 12
200413,508,868Not reported12 of 12
200513,230,192Not reported12 of 12
200612,500,358Not reported12 of 12
200713,281,548Not reported12 of 12
200813,497,339Not reported12 of 12
200913,009,642Not reported12 of 12
201013,172,43788.7%12 of 12
201113,029,48087.8%12 of 12
201213,390,20089.9%12 of 12
201314,320,95896.4%12 of 12
201414,332,32596.5%12 of 12
201511,789,72679.4%12 of 12
201614,610,51898.1%12 of 12
201714,427,64797.2%12 of 12
201813,219,13789.0%12 of 12
201914,172,97795.5%12 of 12
202014,340,15196.3%12 of 12
202113,199,87088.9%12 of 12
202213,926,44193.8%12 of 12
202313,834,66993.2%12 of 12
202412,921,54386.8%12 of 12
202513,218,14189.0%12 of 12
2026 (provisional, partial year)7,477,38886.7%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · PJM

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

Withdrawal, 2024

587,687

million gallons

Consumption, 2024

0

million gallons

Source

James River

Surface, Brackish. Once-through

Watershed stress

Very low/none · 0.160

USGS SUI, HUC12 Lower Chippokes Creek-James River

24 of 24 cooling months report withdrawal. Saline, brackish or ocean intake; not tested. Blank volumes are unreported, not zero.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Nuclear847.5December 1972
2Nuclear847.5May 1973

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Virginia Electric & Power Co as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Surry and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Surry

More plants operated by Virginia Electric & Power Co

Questions about Surry

How much power does Surry produce?

Surry reported 13,218,141 MWh (13.2 TWh) of net generation in 2025, a 89.0% capacity factor on 1,695 MW of nameplate capacity. From January to July 2026 it reported 7.48 TWh, which is provisional.

Where is Surry?

Surry is in Surry County, Virginia, at 37.1661, −76.6986. It is in the PJM Interconnection, LLC balancing area (PJM).

Who operates Surry?

EIA-860M for August 2026 lists Virginia Electric & Power Co as the operator (EIA operator ID 19876). The operator is not always the owner.

When did Surry start operating?

Its first generator began operating in December 1972, according to EIA-860M.

Does InfraMap have power prices for Surry?

Yes. InfraMap has PJM day-ahead and real-time prices at 2 price nodes linked to Surry, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • PJM day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • EIA-923 cooling water 2024 and the USGS surface water supply and use index, Water years 2010-2020 (Oct 2009 to Sep 2020), mean of monthly values
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page