HydroOperatingBPAT

Lower Monumental

Hydro power plant in Walla Walla County, Washington. 675 MW of nameplate capacity across 5 generators, operated by USACE Northwestern Division.

Also known as Lower Monumental Powerhouse · EIA plant 3927

Analyst: free account, 1 question a day.

Little GooseRattlesnake FlatTucannon River Wind FarmIce HarborAdams Nielson SolarRussell D SmithLower Monumental25 km
Open in the map
6 plants within 48 km, from EIA coordinates.

Key facts

Capacity
675 MWNameplate
Generators
5 operatingEIA-860M, August 2026
Operating since
June 1969First generator online
Operator
USACE Northwestern DivisionEIA operator ID 19400
Grid
BPATBalancing authority BPAT
Price nodes
None linkedNo verified ISO node
Location
Walla Walla County, WA46.5635, −118.5397
EIA plant ID
3927EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Lower Monumental produces

Free · EIA-923

Net generation, 2025

1.48 TWh

1,476,976 MWh, final

Capacity factor, 2025

20.8%

2024: 18.0%

January to July 2026

969 GWh

Provisional

Range, 2015 to 2025

1.3–2.8

TWh a year. Low 2024, high 2017

Annual net generation, TWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
20002,344,481Not reported12 of 12
20011,922,664Not reported12 of 12
20022,509,465Not reported12 of 12
20032,104,335Not reported12 of 12
20042,267,584Not reported12 of 12
20051,850,110Not reported12 of 12
20062,755,839Not reported12 of 12
20071,682,562Not reported12 of 12
20082,200,501Not reported12 of 12
20092,416,856Not reported12 of 12
20101,858,85826.2%12 of 12
20113,295,32946.4%12 of 12
20122,520,05135.4%12 of 12
20131,697,01423.9%12 of 12
20142,290,236Not reported12 of 12
20151,640,09523.1%12 of 12
20161,987,13127.9%12 of 12
20172,767,576Not reported12 of 12
20182,383,41833.6%12 of 12
20192,240,943Not reported12 of 12
20201,637,31123.0%12 of 12
20211,338,468Not reported12 of 12
20221,682,64723.7%12 of 12
20231,553,008Not reported12 of 12
20241,281,01418.0%12 of 12
20251,476,97620.8%12 of 12
2026 (provisional, partial year)968,67323.5%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Conventional Hydroelectric135.0June 1969
3Conventional Hydroelectric135.0February 1970
4Conventional Hydroelectric135.0March 1979
5Conventional Hydroelectric135.0April 1979
6Conventional Hydroelectric135.0July 1979

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists USACE Northwestern Division as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Lower Monumental and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Lower Monumental

More plants operated by USACE Northwestern Division

Questions about Lower Monumental

How much power does Lower Monumental produce?

Lower Monumental reported 1,476,976 MWh (1.48 TWh) of net generation in 2025, a 20.8% capacity factor on 675 MW of nameplate capacity. From January to July 2026 it reported 969 GWh, which is provisional.

Where is Lower Monumental?

Lower Monumental is in Walla Walla County, Washington, at 46.5635, −118.5397. It is in the Bonneville Power Administration balancing area (BPAT).

Who operates Lower Monumental?

EIA-860M for August 2026 lists USACE Northwestern Division as the operator (EIA operator ID 19400). The operator is not always the owner.

When did Lower Monumental start operating?

Its first generator began operating in June 1969, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page