HydroOperatingWAUW

Guernsey

Hydro power plant in Platte County, Wyoming. 6.4 MW of nameplate capacity across 2 generators, operated by U S Bureau of Reclamation.

Also known as EIA plant 4178

Analyst: free account, 1 question a day.

Laramie River StationGlendoGuernsey10 km
Open in the map
2 plants within 25 km, from EIA coordinates.

Key facts

Capacity
6.4 MWNameplate
Generators
2 operatingEIA-860M, August 2026
Operating since
July 1927First generator online
Operator
U S Bureau of ReclamationEIA operator ID 2518
Grid
WAUWBalancing authority WAUW
Price nodes
1 SPP nodeResource nodes with prices
Location
Platte County, WY42.2899, −104.7606
EIA plant ID
4178EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Guernsey produces

Free · EIA-923

Net generation, 2025

14.6 GWh

14,570 MWh, final

Capacity factor, 2025

26.0%

2024: 32.1%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

12.0–20.6

GWh a year. Low 2017, high 2020

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
200024,049Not reported12 of 12
200119,430Not reported12 of 12
200210,640Not reported12 of 12
20034,028Not reported12 of 12
20049,755Not reported12 of 12
200510,060Not reported12 of 12
200615,326Not reported12 of 12
200716,021Not reported12 of 12
200817,807Not reported12 of 12
200915,405Not reported12 of 12
201020,58036.7%12 of 12
201125,85346.1%12 of 12
201218,20732.4%12 of 12
20138,71115.5%12 of 12
201415,83828.2%12 of 12
201518,08932.3%12 of 12
201617,94231.9%12 of 12
201712,00421.4%12 of 12
201816,16528.8%12 of 12
201920,32136.2%12 of 12
202020,57236.6%12 of 12
202114,69226.2%12 of 12
202213,62024.3%12 of 12
202318,51533.0%12 of 12
202418,04132.1%12 of 12
202514,57026.0%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · SPP

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Conventional Hydroelectric3.2July 1927
2Conventional Hydroelectric3.2January 1928

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists U S Bureau of Reclamation as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Guernsey and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Guernsey

More plants operated by U S Bureau of Reclamation

Questions about Guernsey

How much power does Guernsey produce?

Guernsey reported 14,570 MWh (14.6 GWh) of net generation in 2025, a 26.0% capacity factor on 6.4 MW of nameplate capacity.

Where is Guernsey?

Guernsey is in Platte County, Wyoming, at 42.2899, −104.7606. It is in the Western Area Power Administration UGP West balancing area (WAUW).

Who operates Guernsey?

EIA-860M for August 2026 lists U S Bureau of Reclamation as the operator (EIA operator ID 2518). The operator is not always the owner.

When did Guernsey start operating?

Its first generator began operating in July 1927, according to EIA-860M.

Does InfraMap have power prices for Guernsey?

Yes. InfraMap has SPP day-ahead and real-time prices at 1 price node linked to Guernsey, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • SPP day-ahead and real-time prices; node and hub assignments as of 2026-10-05

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page