Wood biomassOperatingMISO

WestRock (TX)

Wood biomass power plant in Jasper County, Texas. 57.7 MW of nameplate capacity across 3 generators, operated by WestRock (TX).

Also known as EIA plant 50101

Analyst: free account, 1 question a day.

HEB00048ExxonMobil Beaumont RefineryCottonwood Energy Company LPSabineChickadee G-3WestRock (TX)25 km
Open in the map
6 plants within 43 km, from EIA coordinates.

Key facts

Capacity
57.7 MWNameplate
Generators
3 operatingEIA-860M, August 2026
Operating since
June 1954First generator online
Operator
WestRock (TX)EIA operator ID 12307
Grid
MISOBalancing authority MISO
Price nodes
None linkedNo verified ISO node
Location
Jasper County, TX30.3419, −94.0656
EIA plant ID
50101EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power WestRock (TX) produces

Free · EIA-923

Net generation, 2025

441 GWh

441,162 MWh, final

Capacity factor, 2025

87.3%

2024: 81.9%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

362.9–448.7

GWh a year. Low 2022, high 2019

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000486,371Not reported12 of 12
2001477,289Not reported12 of 12
2002490,038Not reported12 of 12
2003308,422Not reported7 of 12
2004503,338Not reported12 of 12
2005461,220Not reported12 of 12
2006456,838Not reported12 of 12
2007464,980Not reported12 of 12
2008438,844Not reported12 of 12
2009434,732Not reported12 of 12
2010399,47779.0%12 of 12
2011425,84484.3%12 of 12
2012433,76085.6%12 of 12
2013451,08089.2%12 of 12
2014126,76676.3%4 of 12
2015424,08783.9%12 of 12
2016446,85988.2%12 of 12
2017423,34083.8%12 of 12
2018439,67887.0%12 of 12
2019448,73688.8%12 of 12
2020447,09688.2%12 of 12
2021433,16085.7%12 of 12
2022362,88771.8%12 of 12
2023406,76780.5%12 of 12
2024415,15881.9%12 of 12
2025441,16287.3%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
GEN1Wood/Wood Waste Biomass7.5June 1954
GEN2Wood/Wood Waste Biomass32.6May 1965
GEN3Wood/Wood Waste Biomass17.6January 1986

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists WestRock (TX) as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query WestRock (TX) and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near WestRock (TX)

Questions about WestRock (TX)

How much power does WestRock (TX) produce?

WestRock (TX) reported 441,162 MWh (441 GWh) of net generation in 2025, a 87.3% capacity factor on 57.7 MW of nameplate capacity.

Where is WestRock (TX)?

WestRock (TX) is in Jasper County, Texas, at 30.3419, −94.0656. It is in the Midcontinent Independent Transmission System Operator, Inc.. balancing area (MISO).

Who operates WestRock (TX)?

EIA-860M for August 2026 lists WestRock (TX) as the operator (EIA operator ID 12307). The operator is not always the owner.

When did WestRock (TX) start operating?

Its first generator began operating in June 1954, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page