HydroOperatingNEVP

New Lahontan

Hydro power plant in Churchill County, Nevada. 4 MW of nameplate capacity across 1 generator, operated by Truckee-Carson Irrigation District.

Also known as EIA plant 50261

Analyst: free account, 1 question a day.

Patua Acquisition Project, LLCSoda Lake 3Tesla Reno GigaFactoryDesert Peak Power PlantNew Lahontan20 km
Open in the map
6 plants within 34 km, from EIA coordinates.

Key facts

Capacity
4 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
April 1989First generator online
Operator
Truckee-Carson Irrigation DistrictEIA operator ID 40444
Grid
NEVPBalancing authority NEVP
Price nodes
None linkedNo verified ISO node
Location
Churchill County, NV39.4636, −119.0652
EIA plant ID
50261EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power New Lahontan produces

Free · EIA-923

Net generation, 2025

11.7 GWh

11,663 MWh, final

Capacity factor, 2025

33.3%

2024: 28.8%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

2.0–24.4

GWh a year. Low 2015, high 2017

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
20019,141Not reported12 of 12
20028,202Not reported12 of 12
20038,767Not reported12 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
20088,131Not reported12 of 12
20098,975Not reported12 of 12
201010,96831.3%12 of 12
201115,58244.5%12 of 12
20129,70327.6%12 of 12
20136,46218.4%12 of 12
20146,61018.9%12 of 12
20152,0275.8%12 of 12
201610,71630.5%12 of 12
201724,40169.6%12 of 12
201818,33152.3%12 of 12
201915,63144.6%12 of 12
202013,94939.7%12 of 12
20218,05023.0%12 of 12
202210,25929.3%12 of 12
202316,54547.2%12 of 12
202410,10428.8%12 of 12
202511,66333.3%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
GEN1Conventional Hydroelectric4.0April 1989

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Truckee-Carson Irrigation District as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query New Lahontan and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near New Lahontan

More plants operated by Truckee-Carson Irrigation District

Questions about New Lahontan

How much power does New Lahontan produce?

New Lahontan reported 11,663 MWh (11.7 GWh) of net generation in 2025, a 33.3% capacity factor on 4 MW of nameplate capacity.

Where is New Lahontan?

New Lahontan is in Churchill County, Nevada, at 39.4636, −119.0652. It is in the Nevada Power Company balancing area (NEVP).

Who operates New Lahontan?

EIA-860M for August 2026 lists Truckee-Carson Irrigation District as the operator (EIA operator ID 40444). The operator is not always the owner.

When did New Lahontan start operating?

Its first generator began operating in April 1989, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page