CoalOperating

University of Alaska Fairbanks

Coal power plant in Fairbanks North Star, Alaska. 17 MW of nameplate capacity across 1 generator, operated by University of Alaska.

Also known as EIA plant 50711

Analyst: free account, 1 question a day.

FairbanksBattery Energy Storage SystemFWA Central Heat and…North PoleUniversity of Alaska…10 km
Open in the map
5 plants within 26 km, from EIA coordinates.

Key facts

Capacity
17 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
February 2020First generator online
Operator
University of AlaskaEIA operator ID 19511
Grid
Not reported
Price nodes
None linkedNo verified ISO node
Location
Fairbanks North Star, AK64.8542, −147.8221
EIA plant ID
50711EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power University of Alaska Fairbanks produces

Free · EIA-923

Net generation, 2025

67.5 GWh

67,482 MWh, final

Capacity factor, 2025

19.5%

2024: 18.8%

January to July 2026

22.4 GWh

Provisional

Range, 2015 to 2025

28.3–71.0

GWh a year. Low 2019, high 2021

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
200153,202Not reported12 of 12
200250,411Not reported12 of 12
200353,878Not reported12 of 12
200458,657Not reported12 of 12
200559,845Not reported12 of 12
200656,357Not reported12 of 12
200755,539Not reported12 of 12
200848,148Not reported12 of 12
200947,606Not reported12 of 12
201056,98628.8%12 of 12
201156,93828.8%12 of 12
201255,51428.0%12 of 12
201347,55224.0%12 of 12
201447,35523.9%12 of 12
201547,00723.7%12 of 12
201641,06420.7%12 of 12
201742,43921.4%12 of 12
201841,63821.0%12 of 12
201928,32814.3%12 of 12
202045,451Not reported12 of 12
202170,97220.5%12 of 12
202240,43511.7%12 of 12
202368,55719.8%12 of 12
202465,34618.8%12 of 12
202567,48219.5%12 of 12
2026 (provisional, partial year)22,43611.1%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
GEN5Conventional Steam Coal17.0February 2020

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists University of Alaska as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query University of Alaska Fairbanks and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near University of Alaska Fairbanks

Questions about University of Alaska Fairbanks

How much power does University of Alaska Fairbanks produce?

University of Alaska Fairbanks reported 67,482 MWh (67.5 GWh) of net generation in 2025, a 19.5% capacity factor on 17 MW of nameplate capacity. From January to July 2026 it reported 22.4 GWh, which is provisional.

Where is University of Alaska Fairbanks?

University of Alaska Fairbanks is in Fairbanks North Star, Alaska, at 64.8542, −147.8221.

Who operates University of Alaska Fairbanks?

EIA-860M for August 2026 lists University of Alaska as the operator (EIA operator ID 19511). The operator is not always the owner.

When did University of Alaska Fairbanks start operating?

Its first generator began operating in February 2020, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page