WindOperatingMISO

Storm Lake 1

Wind power plant in Buena Vista County, Iowa. 113.9 MW of nameplate capacity across 3 generators, operated by ALLETE Clean Energy.

Also known as Storm Lake I Wind Farm · Storm Lake I · EIA plant 54793

Analyst: free account, 1 question a day.

IntrepidStorm Lake IIRichland (IA)Ida Grove IIStorm Lake 125 km
Open in the map
6 plants within 40 km, from EIA coordinates.

Key facts

Capacity
113.9 MWNameplate
Generators
3 operatingEIA-860M, August 2026
Operating since
May 1999First generator online
Operator
ALLETE Clean EnergyEIA operator ID 59496
Grid
MISOBalancing authority MISO
Price nodes
1 MISO nodeResource nodes with prices
Location
Buena Vista County, IA42.6878, −95.4050
EIA plant ID
54793EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Storm Lake 1 produces

Free · EIA-923

Net generation, 2025

86.9 GWh

86,924 MWh, final

Capacity factor, 2025

8.7%

2024: 8.5%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

84.7–222.3

GWh a year. Low 2024, high 2016

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000287,270Not reported12 of 12
2001281,969Not reported12 of 12
2002383,809Not reported12 of 12
2003283,507Not reported12 of 12
2004284,832Not reported12 of 12
2005272,806Not reported12 of 12
2006287,306Not reported12 of 12
2007293,057Not reported12 of 12
2008279,663Not reported12 of 12
2009237,777Not reported12 of 12
2010233,95723.4%12 of 12
2011263,42326.4%12 of 12
2012275,55627.5%12 of 12
2013216,66821.7%12 of 12
2014196,89719.7%12 of 12
2015203,27620.4%12 of 12
2016222,30222.2%12 of 12
2017214,57821.5%12 of 12
2018192,91619.3%12 of 12
2019189,89219.0%12 of 12
2020207,288Not reported12 of 12
202198,3499.9%12 of 12
2022109,57911.0%12 of 12
202394,4749.5%12 of 12
202484,6928.5%12 of 12
202586,9248.7%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · MISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
2Onshore Wind Turbine0.7June 1999
3Onshore Wind Turbine0.7June 1999
EXISOnshore Wind Turbine112.5May 1999

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists ALLETE Clean Energy as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Storm Lake 1 and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Storm Lake 1

More plants operated by ALLETE Clean Energy

Questions about Storm Lake 1

How much power does Storm Lake 1 produce?

Storm Lake 1 reported 86,924 MWh (86.9 GWh) of net generation in 2025, a 8.7% capacity factor on 113.9 MW of nameplate capacity.

Where is Storm Lake 1?

Storm Lake 1 is in Buena Vista County, Iowa, at 42.6878, −95.4050. It is in the Midcontinent Independent Transmission System Operator, Inc.. balancing area (MISO).

Who operates Storm Lake 1?

EIA-860M for August 2026 lists ALLETE Clean Energy as the operator (EIA operator ID 59496). The operator is not always the owner.

When did Storm Lake 1 start operating?

Its first generator began operating in May 1999, according to EIA-860M.

Does InfraMap have power prices for Storm Lake 1?

Yes. InfraMap has MISO day-ahead and real-time prices at 1 price node linked to Storm Lake 1, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • MISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)
  • Project names from the USGS U.S. Wind Turbine Database

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page