Natural gasOperatingCAISO

High Desert Power Plant

Natural gas power plant in San Bernardino County, California. 960 MW of nameplate capacity across 4 generators, operated by MRP Generation Holdings, LLC.

Also known as EIA plant 55518

Analyst: free account, 1 question a day.

Expressway Solar C2Expressway Solar AAdelanto Solar, LLCAdelanto Solar II, LLCHudson - High Desert HybridHigh Desert2 km
Open in the map
6 plants within 4.6 km, from EIA coordinates.

Key facts

Capacity
960 MWNameplate
Generators
4 operatingEIA-860M, August 2026
Operating since
April 2003First generator online
Operator
MRP Generation Holdings, LLCEIA operator ID 60431
Grid
CAISOBalancing authority CISO
Price nodes
1 CAISO nodeResource nodes with prices
Location
San Bernardino County, CA34.5953, −117.3647
EIA plant ID
55518EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power High Desert produces

Free · EIA-923

Net generation, 2025

3.33 TWh

3,333,774 MWh, final

Capacity factor, 2025

39.6%

2024: 54.5%

January to July 2026

1.18 TWh

Provisional

Range, 2015 to 2025

2.2–4.6

TWh a year. Low 2017, high 2024

Annual net generation, TWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
20032,318,686Not reported9 of 12
20043,785,083Not reported12 of 12
20053,656,116Not reported12 of 12
20063,926,682Not reported12 of 12
20074,518,068Not reported12 of 12
20084,704,901Not reported12 of 12
20094,265,280Not reported12 of 12
20103,283,954Not reported12 of 12
20111,938,136Not reported12 of 12
20125,040,04267.3%12 of 12
20134,591,241Not reported12 of 12
20143,964,94053.1%12 of 12
20153,542,24047.5%12 of 12
20163,089,84141.3%12 of 12
20172,168,001Not reported12 of 12
20183,019,302Not reported12 of 12
20193,337,42644.7%12 of 12
20203,056,55040.8%12 of 12
20213,803,880Not reported12 of 12
20224,052,35554.3%12 of 12
20234,075,232Not reported12 of 12
20244,596,08754.5%12 of 12
20253,333,77439.6%12 of 12
2026 (provisional, partial year)1,175,89824.1%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · CAISO

Emissions

Free · EPA CAMPD

CO₂, 2025

1.43M

US short tons. 2024: 1.99M

SO₂, 2025

7

US short tons

NOx, 2025

83

US short tons

CO₂ per MWh, calculated

0.43 t

About 858 lb per MWh

3 of 3 EPA units reported CO₂ in 2025 (CTG1, CTG2, CTG3), matched to EIA plant 55518 through the EPA–EIA crosswalk. The per-MWh rate is EPA CO₂ divided by EIA-923 net generation. The two reporting boundaries can differ.

Water use

Free · EIA-923 cooling, USGS

Withdrawal, 2024

979

million gallons

Consumption, 2024

978

million gallons

Source

Municipal

Surface, Fresh. Induced-draft tower

Watershed stress

Low · 0.368

USGS SUI, HUC12 Burkhardt Lake-Mojave River

12 of 12 cooling months report withdrawal. SUI of the HUC12 containing the plant. Blank volumes are unreported, not zero.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
CTG1Natural Gas Fired Combined Cycle209.0April 2003
CTG2Natural Gas Fired Combined Cycle209.0April 2003
CTG3Natural Gas Fired Combined Cycle209.0April 2003
STG1Natural Gas Fired Combined Cycle333.0April 2003

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists MRP Generation Holdings, LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query High Desert Power Plant and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near High Desert

Questions about High Desert

How much power does High Desert Power Plant produce?

High Desert Power Plant reported 3,333,774 MWh (3.33 TWh) of net generation in 2025, a 39.6% capacity factor on 960 MW of nameplate capacity. From January to July 2026 it reported 1.18 TWh, which is provisional.

Where is High Desert Power Plant?

High Desert Power Plant is in San Bernardino County, California, at 34.5953, −117.3647. It is in the California Independent System Operator balancing area (CISO).

Who operates High Desert Power Plant?

EIA-860M for August 2026 lists MRP Generation Holdings, LLC as the operator (EIA operator ID 60431). The operator is not always the owner.

When did High Desert Power Plant start operating?

Its first generator began operating in April 2003, according to EIA-860M.

Does InfraMap have power prices for High Desert Power Plant?

Yes. InfraMap has CAISO day-ahead and real-time prices at 1 price node linked to High Desert Power Plant, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • EPA CAMPD annual emissions through the EPA–EIA crosswalk, 1995 to 2025
  • CAISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • EIA-923 cooling water 2024 and the USGS surface water supply and use index, Water years 2010-2020 (Oct 2009 to Sep 2020), mean of monthly values

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page