WindOperatingPSCO

Twin Buttes Wind Project

Wind power plant in Bent County, Colorado. 75 MW of nameplate capacity across 1 generator, operated by Avangrid Power LLC.

Also known as Twin Buttes · EIA plant 56460

Analyst: free account, 1 question a day.

Colorado Green Holdings LLCTwin Buttes II WindVilas Solar ArrayLamar PlantLas AnimasTwin Buttes Wind Proj…25 km
Open in the map
5 plants within 53 km, from EIA coordinates.

Key facts

Capacity
75 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
July 2007First generator online
Operator
Avangrid Power LLCEIA operator ID 15399
Grid
PSCOBalancing authority PSCO
Price nodes
None linkedNo verified ISO node
Location
Bent County, CO37.6735, −102.8622
EIA plant ID
56460EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Twin Buttes Wind Project produces

Free · EIA-923

Net generation, 2025

228 GWh

228,171 MWh, final

Capacity factor, 2025

34.7%

2024: 35.4%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

171.2–265.4

GWh a year. Low 2021, high 2020

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007128,688Not reported12 of 12
2008265,378Not reported12 of 12
2009256,708Not reported12 of 12
2010269,36341.0%12 of 12
2011245,60137.4%12 of 12
2012263,99740.1%12 of 12
2013251,04738.2%12 of 12
2014240,92336.7%12 of 12
2015237,72236.2%12 of 12
2016262,25939.8%12 of 12
2017230,03935.0%12 of 12
2018257,25439.2%12 of 12
2019239,68736.5%12 of 12
2020265,37240.3%12 of 12
2021171,16526.1%12 of 12
2022206,78031.5%12 of 12
2023218,98933.3%12 of 12
2024232,98435.4%12 of 12
2025228,17134.7%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
WT1Onshore Wind Turbine75.0July 2007

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Avangrid Power LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Twin Buttes Wind Project and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Twin Buttes Wind Project

More plants operated by Avangrid Power LLC

Questions about Twin Buttes Wind Project

How much power does Twin Buttes Wind Project produce?

Twin Buttes Wind Project reported 228,171 MWh (228 GWh) of net generation in 2025, a 34.7% capacity factor on 75 MW of nameplate capacity.

Where is Twin Buttes Wind Project?

Twin Buttes Wind Project is in Bent County, Colorado, at 37.6735, −102.8622. It is in the Public Service Company of Colorado balancing area (PSCO).

Who operates Twin Buttes Wind Project?

EIA-860M for August 2026 lists Avangrid Power LLC as the operator (EIA operator ID 15399). The operator is not always the owner.

When did Twin Buttes Wind Project start operating?

Its first generator began operating in July 2007, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • Project names from the USGS U.S. Wind Turbine Database

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page