Natural gasOperatingERCOT

Winchester Power Park

Natural gas power plant in Fayette County, Texas. 242 MW of nameplate capacity across 4 generators, operated by Lower Colorado River Authority.

Also known as EIA plant 56674

Analyst: free account, 1 question a day.

7V Solar RanchFayette Power ProjectSim GideonBig Star Solar, LLC (Hybrid)Winchester Power Park10 km
Open in the map
5 plants within 30 km, from EIA coordinates.

Key facts

Capacity
242 MWNameplate
Generators
4 operatingEIA-860M, August 2026
Operating since
May 2010First generator online
Operator
Lower Colorado River AuthorityEIA operator ID 11269
Grid
ERCOTBalancing authority ERCO
Price nodes
2 ERCOT nodesResource nodes with prices
Location
Fayette County, TX30.0255, −96.9945
EIA plant ID
56674EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Winchester Power Park produces

Free · EIA-923

Net generation, 2025

58.1 GWh

58,082 MWh, final

Capacity factor, 2025

2.7%

2024: 2.4%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

28.2–86.2

GWh a year. Low 2015, high 2023

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010182,526Not reported9 of 12
201175,9403.6%12 of 12
201246,3462.2%12 of 12
201329,3541.4%12 of 12
201490,9674.3%12 of 12
201528,2431.3%12 of 12
201641,7972.0%12 of 12
201764,0813.0%12 of 12
201838,3091.8%12 of 12
201946,1232.2%12 of 12
202030,1571.4%12 of 12
202170,9753.3%12 of 12
202284,3784.0%12 of 12
202386,2384.1%12 of 12
202451,5452.4%12 of 12
202558,0822.7%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · ERCOT

Emissions

Free · EPA CAMPD

CO₂, 2025

32,718

US short tons. 2024: 29,305

SO₂, 2025

0

US short tons

NOx, 2025

3

US short tons

CO₂ per MWh, calculated

0.56 t

About 1,127 lb per MWh

4 of 4 EPA units reported CO₂ in 2025 (1, 2, 3, 4), matched to EIA plant 56674 through the EPA–EIA crosswalk. The per-MWh rate is EPA CO₂ divided by EIA-923 net generation. The two reporting boundaries can differ.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
CGT1Natural Gas Fired Combustion Turbine60.5May 2010
CGT2Natural Gas Fired Combustion Turbine60.5May 2010
CGT3Natural Gas Fired Combustion Turbine60.5May 2010
CGT4Natural Gas Fired Combustion Turbine60.5May 2010

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Lower Colorado River Authority as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Winchester Power Park and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Winchester Power Park

More plants operated by Lower Colorado River Authority

Questions about Winchester Power Park

How much power does Winchester Power Park produce?

Winchester Power Park reported 58,082 MWh (58.1 GWh) of net generation in 2025, a 2.7% capacity factor on 242 MW of nameplate capacity.

Where is Winchester Power Park?

Winchester Power Park is in Fayette County, Texas, at 30.0255, −96.9945. It is in the Electric Reliability Council of Texas, Inc. balancing area (ERCO).

Who operates Winchester Power Park?

EIA-860M for August 2026 lists Lower Colorado River Authority as the operator (EIA operator ID 11269). The operator is not always the owner.

When did Winchester Power Park start operating?

Its first generator began operating in May 2010, according to EIA-860M.

Does InfraMap have power prices for Winchester Power Park?

Yes. InfraMap has ERCOT day-ahead and real-time prices at 2 price nodes linked to Winchester Power Park, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • EPA CAMPD annual emissions through the EPA–EIA crosswalk, 1995 to 2025
  • ERCOT day-ahead and real-time prices; node and hub assignments as of 2026-10-05

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page