Notrees Windpower Hybrid

Wind project in Ector County, Texas. 188.5 MW of nameplate capacity across 3 generators, operated by Deriva Energy.

Also known as Notrees · EIA plant 56961

This project groups Notrees Windpower Hybrid (EIA 56961). EIA reports them as separate plants.

Analyst: free account, 1 question a day.

Phoebe SolarGoldsmithNon-PLD US-El Paso -…Ector County Energy CenterSwift Air Solar INotrees Windpower Hyb…10 km
Open in the map
6 plants within 28 km, from EIA coordinates.

Key facts

Capacity
188.5 MWWind 152.5 · Battery storage 36.0
Generators
3 operatingEIA-860M, August 2026
Operating since
April 2009First generator online
Operator
Deriva EnergyEIA operator ID 65411
Grid
ERCOTBalancing authority ERCO
Price nodes
1 ERCOT nodeResource nodes with prices
Location
Ector County, TX31.9950, −102.8283
EIA plant ID
56961EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Notrees Windpower Hybrid produces

Free · EIA-923

Net generation, 2025

237 GWh

237,051 MWh, final

Capacity factor, 2025

18.1%

2024: 19.6%

January to July 2026

129 GWh

Provisional

Range, 2015 to 2025

237.1–422.5

GWh a year. Low 2025, high 2017

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009274,204Not reported9 of 12
2010440,20333.0%12 of 12
2011398,96029.9%12 of 12
201236,226Not reported1 of 12
2013455,51934.1%12 of 12
2014175,54340.0%4 of 12
2015389,735Not reported12 of 12
2016411,82030.8%12 of 12
2017422,50431.8%12 of 12
2018396,78429.9%12 of 12
2019394,34429.7%12 of 12
2020388,66429.1%12 of 12
2021313,92323.7%12 of 12
2022306,17023.1%12 of 12
2023257,57219.4%12 of 12
2024260,54219.6%12 of 12
2025237,05118.1%12 of 12
2026 (provisional, partial year)128,68616.8%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · ERCOT

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
BATTBatteries36.0December 2012
GEOnshore Wind Turbine60.0April 2009
VESTAOnshore Wind Turbine92.5April 2009

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Deriva Energy as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Notrees Windpower Hybrid and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Notrees Windpower Hybrid

More plants operated by Deriva Energy

Questions about Notrees Windpower Hybrid

How much power does Notrees Windpower Hybrid produce?

Notrees Windpower Hybrid reported 237,051 MWh (237 GWh) of net generation in 2025, a 18.1% capacity factor on 188.5 MW of nameplate capacity. From January to July 2026 it reported 129 GWh, which is provisional.

Where is Notrees Windpower Hybrid?

Notrees Windpower Hybrid is in Ector County, Texas, at 31.9950, −102.8283. It is in the Electric Reliability Council of Texas, Inc. balancing area (ERCO).

Who operates Notrees Windpower Hybrid?

EIA-860M for August 2026 lists Deriva Energy as the operator (EIA operator ID 65411). The operator is not always the owner.

When did Notrees Windpower Hybrid start operating?

Its first generator began operating in April 2009, according to EIA-860M.

Does InfraMap have power prices for Notrees Windpower Hybrid?

Yes. InfraMap has ERCOT day-ahead and real-time prices at 1 price node linked to Notrees Windpower Hybrid, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • ERCOT day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Project names from the USGS U.S. Wind Turbine Database

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page