WindOperatingNA

Delta Wind Farm

Wind power plant in Southeast Fairbanks, Alaska. 1.9 MW of nameplate capacity across 3 generators, operated by Alaska Environmental Power.

Also known as Delta Junction · EIA plant 58511

Analyst: free account, 1 question a day.

Delta Wind Farm500 m
Open in the map
No other mapped plant within 60 km.

Key facts

Capacity
1.9 MWNameplate
Generators
3 operatingEIA-860M, August 2026
Operating since
September 2008First generator online
Operator
Alaska Environmental PowerEIA operator ID 58488
Grid
NABalancing authority NA
Price nodes
None linkedNo verified ISO node
Location
Southeast Fairbanks, AK64.0139, −145.5967
EIA plant ID
58511EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Delta Wind Farm produces

Free · EIA-923

Net generation, 2025

4.24 GWh

4,244 MWh, final

Capacity factor, 2025

25.5%

2024: 23.2%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

2.6–4.5

GWh a year. Low 2017, high 2018

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
20131,600Not reported12 of 12
20144,50027.0%12 of 12
20154,00024.0%12 of 12
20164,44626.6%12 of 12
20172,60715.7%12 of 12
20184,49827.0%12 of 12
20193,97023.9%12 of 12
20203,84923.1%12 of 12
20213,65422.0%12 of 12
20223,95523.8%12 of 12
20233,98323.9%12 of 12
20243,87123.2%12 of 12
20254,24425.5%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
EWT1Onshore Wind Turbine0.9October 2009
EWT2Onshore Wind Turbine0.9September 2013
NW1Onshore Wind Turbine0.1September 2008

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Alaska Environmental Power as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Delta Wind Farm and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Delta Wind Farm

Questions about Delta Wind Farm

How much power does Delta Wind Farm produce?

Delta Wind Farm reported 4,244 MWh (4.24 GWh) of net generation in 2025, a 25.5% capacity factor on 1.9 MW of nameplate capacity.

Where is Delta Wind Farm?

Delta Wind Farm is in Southeast Fairbanks, Alaska, at 64.0139, −145.5967. It is in the No BA balancing area (NA).

Who operates Delta Wind Farm?

EIA-860M for August 2026 lists Alaska Environmental Power as the operator (EIA operator ID 58488). The operator is not always the owner.

When did Delta Wind Farm start operating?

Its first generator began operating in September 2008, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • Project names from the USGS U.S. Wind Turbine Database

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page