Stuyvesant Falls
Hydro power plant in Columbia County, New York. 6 MW of nameplate capacity across 2 generators, operated by Albany Engineering Corporation.
Also known as Stuyvesant Falls Hydroelectric Station · EIA plant 58873
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 6 MWNameplate
- Generators
- 2 operatingEIA-860M, August 2026
- Operating since
- December 2012First generator online
- Operator
- Albany Engineering CorporationEIA operator ID 58756
- Grid
- NYISOBalancing authority NYIS
- Price nodes
- None linkedNo verified ISO node
- Location
- Columbia County, NY42.3514, −73.7339
- EIA plant ID
- 58873EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Stuyvesant Falls produces
Free · EIA-923Net generation, 2025
13.0 GWh
12,971 MWh, final
Capacity factor, 2025
24.7%
2024: 22.6%
January to July 2026
Not reported
Provisional. 0 of 7 months reported
Range, 2015 to 2025
9.6–22.8
GWh a year. Low 2016, high 2021
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | Not reported | Not reported | 0 of 12 |
| 2006 | Not reported | Not reported | 0 of 12 |
| 2007 | Not reported | Not reported | 0 of 12 |
| 2008 | Not reported | Not reported | 0 of 12 |
| 2009 | Not reported | Not reported | 0 of 12 |
| 2010 | Not reported | Not reported | 0 of 12 |
| 2011 | Not reported | Not reported | 0 of 12 |
| 2012 | Not reported | Not reported | 0 of 12 |
| 2013 | 9,309 | 17.7% | 12 of 12 |
| 2014 | 12,292 | 23.4% | 12 of 12 |
| 2015 | 9,626 | 18.3% | 12 of 12 |
| 2016 | 9,564 | 18.1% | 12 of 12 |
| 2017 | 14,597 | 27.8% | 12 of 12 |
| 2018 | 19,489 | 37.1% | 12 of 12 |
| 2019 | 13,141 | 25.0% | 12 of 12 |
| 2020 | 12,755 | 24.2% | 12 of 12 |
| 2021 | 22,798 | 43.4% | 12 of 12 |
| 2022 | 13,933 | 26.5% | 12 of 12 |
| 2023 | 22,148 | 42.1% | 12 of 12 |
| 2024 | 11,915 | 22.6% | 12 of 12 |
| 2025 | 12,971 | 24.7% | 12 of 12 |
| 2026 (provisional, partial year) | Not reported | Not reported | 0 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free accountNo verified ISO price node is linked to this plant, or its price history could not load.
Emissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| UNIT1 | Conventional Hydroelectric | 3.0 | December 2012 |
| UNIT2 | Conventional Hydroelectric | 3.0 | December 2012 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Albany Engineering Corporation as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
300 analyst questions a month, plus MCP
Query Stuyvesant Falls and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Stuyvesant Falls
More plants operated by Albany Engineering Corporation
Questions about Stuyvesant Falls
How much power does Stuyvesant Falls produce?
Stuyvesant Falls reported 12,971 MWh (13.0 GWh) of net generation in 2025, a 24.7% capacity factor on 6 MW of nameplate capacity.
Where is Stuyvesant Falls?
Stuyvesant Falls is in Columbia County, New York, at 42.3514, −73.7339. It is in the New York Independent System Operator balancing area (NYIS).
Who operates Stuyvesant Falls?
EIA-860M for August 2026 lists Albany Engineering Corporation as the operator (EIA operator ID 58756). The operator is not always the owner.
When did Stuyvesant Falls start operating?
Its first generator began operating in December 2012, according to EIA-860M.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
- Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page