OilOperatingNA

Swampy Acres Microgrid

Oil power plant in Kodiak Island, Alaska. 8.4 MW of nameplate capacity across 3 generators, operated by Kodiak Electric Assn Inc.

Also known as EIA plant 60250

Analyst: free account, 1 question a day.

Nymans Plant MicrogridKodiak MicrogridPort Lions MicrogridTerror Lake MicrogridSwampy Acres Microgrid10 km
Open in the map
6 plants within 27 km, from EIA coordinates.

Key facts

Capacity
8.4 MWNameplate
Generators
3 operatingEIA-860M, August 2026
Operating since
February 2002First generator online
Operator
Kodiak Electric Assn IncEIA operator ID 10433
Grid
NABalancing authority NA
Price nodes
None linkedNo verified ISO node
Location
Kodiak Island, AK57.7756, −152.4803
EIA plant ID
60250EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Swampy Acres Microgrid produces

Free · EIA-923

Net generation, 2025

0 MWh

0 MWh, final

Capacity factor, 2025

0.0%

2024: 0.0%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

0.0–36.0

MWh a year. Low 2015, high 2017

Annual net generation, MWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
20150Not reported12 of 12
201600.0%12 of 12
2017360.0%12 of 12
201800.0%12 of 12
201900.0%12 of 12
202000.0%12 of 12
202140.0%12 of 12
202200.0%12 of 12
202300.0%12 of 12
202400.0%12 of 12
202500.0%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
6APetroleum Liquids2.0June 2002
7APetroleum Liquids2.0February 2002
13Petroleum Liquids4.4April 2015

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Kodiak Electric Assn Inc as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Swampy Acres Microgrid and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Swampy Acres Microgrid

More plants operated by Kodiak Electric Assn Inc

Questions about Swampy Acres Microgrid

How much power does Swampy Acres Microgrid produce?

Swampy Acres Microgrid reported 0 MWh (0 MWh) of net generation in 2025.

Where is Swampy Acres Microgrid?

Swampy Acres Microgrid is in Kodiak Island, Alaska, at 57.7756, −152.4803. It is in the No BA balancing area (NA).

Who operates Swampy Acres Microgrid?

EIA-860M for August 2026 lists Kodiak Electric Assn Inc as the operator (EIA operator ID 10433). The operator is not always the owner.

When did Swampy Acres Microgrid start operating?

Its first generator began operating in February 2002, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page