Upland Prairie
Wind power plant in Clay County, Iowa. 299.3 MW of nameplate capacity across 1 generator, operated by Interstate Power and Light Co.
Also known as EIA plant 61564
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 299.3 MWNameplate
- Generators
- 1 operatingEIA-860M, August 2026
- Operating since
- March 2019First generator online
- Operator
- Interstate Power and Light CoEIA operator ID 9417
- Grid
- MISOBalancing authority MISO
- Price nodes
- 1 MISO nodeResource nodes with prices
- Location
- Clay County, IA43.2074, −95.3494
- EIA plant ID
- 61564EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Upland Prairie produces
Free · EIA-923Net generation, 2025
1.08 TWh
1,084,946 MWh, final
Capacity factor, 2025
41.4%
2024: 41.5%
January to July 2026
645 GWh
Provisional
Range, 2020 to 2025
0.9–1.2
TWh a year. Low 2021, high 2022
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | Not reported | Not reported | 0 of 12 |
| 2006 | Not reported | Not reported | 0 of 12 |
| 2007 | Not reported | Not reported | 0 of 12 |
| 2008 | Not reported | Not reported | 0 of 12 |
| 2009 | Not reported | Not reported | 0 of 12 |
| 2010 | Not reported | Not reported | 0 of 12 |
| 2011 | Not reported | Not reported | 0 of 12 |
| 2012 | Not reported | Not reported | 0 of 12 |
| 2013 | Not reported | Not reported | 0 of 12 |
| 2014 | Not reported | Not reported | 0 of 12 |
| 2015 | Not reported | Not reported | 0 of 12 |
| 2016 | Not reported | Not reported | 0 of 12 |
| 2017 | Not reported | Not reported | 0 of 12 |
| 2018 | Not reported | Not reported | 0 of 12 |
| 2019 | 771,294 | Not reported | 10 of 12 |
| 2020 | 1,040,479 | 39.6% | 12 of 12 |
| 2021 | 869,137 | 33.1% | 12 of 12 |
| 2022 | 1,190,864 | 45.4% | 12 of 12 |
| 2023 | 1,063,249 | 40.6% | 12 of 12 |
| 2024 | 1,091,512 | 41.5% | 12 of 12 |
| 2025 | 1,084,946 | 41.4% | 12 of 12 |
| 2026 (provisional, partial year) | 645,326 | 42.4% | 7 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free account · MISOEmissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| 1 | Onshore Wind Turbine | 299.3 | March 2019 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Interstate Power and Light Co as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Modeled curtailment
A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.
Expected vs reported generation
Monthly modeled expected output and physical potential next to EIA-923 reported output.
300 analyst questions a month, plus MCP
Query Upland Prairie and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Upland Prairie
More plants operated by Interstate Power and Light Co
Questions about Upland Prairie
How much power does Upland Prairie produce?
Upland Prairie reported 1,084,946 MWh (1.08 TWh) of net generation in 2025, a 41.4% capacity factor on 299.3 MW of nameplate capacity. From January to July 2026 it reported 645 GWh, which is provisional.
Where is Upland Prairie?
Upland Prairie is in Clay County, Iowa, at 43.2074, −95.3494. It is in the Midcontinent Independent Transmission System Operator, Inc.. balancing area (MISO).
Who operates Upland Prairie?
EIA-860M for August 2026 lists Interstate Power and Light Co as the operator (EIA operator ID 9417). The operator is not always the owner.
When did Upland Prairie start operating?
Its first generator began operating in March 2019, according to EIA-860M.
Does InfraMap have power prices for Upland Prairie?
Yes. InfraMap has MISO day-ahead and real-time prices at 1 price node linked to Upland Prairie, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
- MISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page