Kingsberry Energy Storage System
Battery storage project in Travis County, Texas. 1.5 MW of nameplate capacity across 1 generator, operated by Austin Energy.
Also known as EIA plant 61741
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 1.5 MWNameplate
- Generators
- 1 operatingEIA-860M, August 2026
- Operating since
- September 2018First generator online
- Operator
- Austin EnergyEIA operator ID 1015
- Grid
- ERCOTBalancing authority ERCO
- Price nodes
- None linkedNo verified ISO node
- Location
- Travis County, TX30.2660, −97.6861
- EIA plant ID
- 61741EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Kingsberry Energy Storage System produces
Free · EIA-923Net generation, 2025
−58 MWh
−58 MWh, final
Battery discharge, 2025
0 MWh
Charge 58 MWh
January to July 2026
Not reported
Provisional. 0 of 7 months reported
Range, 2019 to 2025
−182.0–−19.0
MWh a year. Low 2020, high 2023
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | Not reported | Not reported | 0 of 12 |
| 2006 | Not reported | Not reported | 0 of 12 |
| 2007 | Not reported | Not reported | 0 of 12 |
| 2008 | Not reported | Not reported | 0 of 12 |
| 2009 | Not reported | Not reported | 0 of 12 |
| 2010 | Not reported | Not reported | 0 of 12 |
| 2011 | Not reported | Not reported | 0 of 12 |
| 2012 | Not reported | Not reported | 0 of 12 |
| 2013 | Not reported | Not reported | 0 of 12 |
| 2014 | Not reported | Not reported | 0 of 12 |
| 2015 | Not reported | Not reported | 0 of 12 |
| 2016 | Not reported | Not reported | 0 of 12 |
| 2017 | Not reported | Not reported | 0 of 12 |
| 2018 | −354 | Not reported | 4 of 12 |
| 2019 | −116 | Not reported | 12 of 12 |
| 2020 | −182 | Not reported | 12 of 12 |
| 2021 | −174 | Not reported | 12 of 12 |
| 2022 | −103 | Not reported | 12 of 12 |
| 2023 | −19 | Not reported | 12 of 12 |
| 2024 | −56 | Not reported | 12 of 12 |
| 2025 | −58 | Not reported | 12 of 12 |
| 2026 (provisional, partial year) | Not reported | Not reported | 0 of 7 |
* 2026 covers January to July and is provisional. Battery plants can report negative net generation, when charging uses more energy than they discharge.
Power prices and basis
Free accountNo verified ISO price node is linked to this plant, or its price history could not load.
Emissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| KBESS | Batteries | 1.5 | September 2018 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Austin Energy as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
300 analyst questions a month, plus MCP
Query Kingsberry Energy Storage System and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Kingsberry Energy Storage System
More plants operated by Austin Energy
Questions about Kingsberry Energy Storage System
How much power does Kingsberry Energy Storage System produce?
Kingsberry Energy Storage System reported −58 MWh (−58 MWh) of net generation in 2025.
Where is Kingsberry Energy Storage System?
Kingsberry Energy Storage System is in Travis County, Texas, at 30.2660, −97.6861. It is in the Electric Reliability Council of Texas, Inc. balancing area (ERCO).
Who operates Kingsberry Energy Storage System?
EIA-860M for August 2026 lists Austin Energy as the operator (EIA operator ID 1015). The operator is not always the owner.
When did Kingsberry Energy Storage System start operating?
Its first generator began operating in September 2018, according to EIA-860M.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page