232 Long Branch 29 Solar I, LLC
Solar power plant in Cleveland County, North Carolina. 2 MW of nameplate capacity across 1 generator, operated by Cardinal Renewables.
Also known as EIA plant 63296
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 2 MWNameplate
- Generators
- 1 operatingEIA-860M, August 2026
- Operating since
- August 2018First generator online
- Operator
- Cardinal RenewablesEIA operator ID 62627
- Grid
- DUKBalancing authority DUK
- Price nodes
- None linkedNo verified ISO node
- Location
- Cleveland County, NC35.2322, −81.5597
- EIA plant ID
- 63296EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power 232 Long Branch 29 Solar I produces
Free · EIA-923Net generation, 2025
2.25 GWh
2,245 MWh, final
Capacity factor, 2025
12.8%
2024: 12.2%
January to July 2026
Not reported
Provisional. 0 of 7 months reported
Range, 2019 to 2025
2.1–2.5
GWh a year. Low 2024, high 2019
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | Not reported | Not reported | 0 of 12 |
| 2006 | Not reported | Not reported | 0 of 12 |
| 2007 | Not reported | Not reported | 0 of 12 |
| 2008 | Not reported | Not reported | 0 of 12 |
| 2009 | Not reported | Not reported | 0 of 12 |
| 2010 | Not reported | Not reported | 0 of 12 |
| 2011 | Not reported | Not reported | 0 of 12 |
| 2012 | Not reported | Not reported | 0 of 12 |
| 2013 | Not reported | Not reported | 0 of 12 |
| 2014 | Not reported | Not reported | 0 of 12 |
| 2015 | Not reported | Not reported | 0 of 12 |
| 2016 | Not reported | Not reported | 0 of 12 |
| 2017 | Not reported | Not reported | 0 of 12 |
| 2018 | Not reported | Not reported | 0 of 12 |
| 2019 | 2,491 | 14.2% | 12 of 12 |
| 2020 | 2,421 | 13.8% | 12 of 12 |
| 2021 | 2,477 | 14.1% | 12 of 12 |
| 2022 | 2,380 | 13.6% | 12 of 12 |
| 2023 | 2,272 | 13.0% | 12 of 12 |
| 2024 | 2,135 | 12.2% | 12 of 12 |
| 2025 | 2,245 | 12.8% | 12 of 12 |
| 2026 (provisional, partial year) | Not reported | Not reported | 0 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free accountNo verified ISO price node is linked to this plant, or its price history could not load.
Emissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| NCLFT | Solar Photovoltaic | 2.0 | August 2018 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Cardinal Renewables as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Modeled curtailment
A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.
Expected vs reported generation
Monthly modeled expected output and physical potential next to EIA-923 reported output.
300 analyst questions a month, plus MCP
Query 232 Long Branch 29 Solar I, LLC and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near 232 Long Branch 29 Solar I
More plants operated by Cardinal Renewables
Questions about 232 Long Branch 29 Solar I
How much power does 232 Long Branch 29 Solar I, LLC produce?
232 Long Branch 29 Solar I, LLC reported 2,245 MWh (2.25 GWh) of net generation in 2025, a 12.8% capacity factor on 2 MW of nameplate capacity.
Where is 232 Long Branch 29 Solar I, LLC?
232 Long Branch 29 Solar I, LLC is in Cleveland County, North Carolina, at 35.2322, −81.5597. It is in the Duke Energy Carolinas balancing area (DUK).
Who operates 232 Long Branch 29 Solar I, LLC?
EIA-860M for August 2026 lists Cardinal Renewables as the operator (EIA operator ID 62627). The operator is not always the owner.
When did 232 Long Branch 29 Solar I, LLC start operating?
Its first generator began operating in August 2018, according to EIA-860M.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page