Solar and battery storage project in Orange County, New York. 8.4 MW of nameplate capacity across 2 generators, operated by FFP NY Goshen Project1, LLC.
Also known as EIA plant 67281
This project groups FFP - NY Urbanski (EIA 67281). EIA reports them as separate plants.
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 8.4 MWSolar 4.4 · Battery storage 4.0
- Generators
- 2 operatingEIA-860M, August 2026
- Operating since
- April 2024First generator online
- Operator
- FFP NY Goshen Project1, LLCEIA operator ID 66147
- Grid
- NYISOBalancing authority NYIS
- Price nodes
- None linkedNo verified ISO node
- Location
- Orange County, NY41.3309, −74.4034
- EIA plant ID
- 67281EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power FFP - NY Urbanski produces
Free · EIA-923Net generation, 2025
4.13 GWh
4,125 MWh, final
Capacity factor, 2025
10.7%
2024: Not reported
January to July 2026
Not reported
Provisional. 0 of 7 months reported
Range, 2024 to 2025
4.1–4.7
GWh a year. Low 2025, high 2024
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | Not reported | Not reported | 0 of 12 |
| 2006 | Not reported | Not reported | 0 of 12 |
| 2007 | Not reported | Not reported | 0 of 12 |
| 2008 | Not reported | Not reported | 0 of 12 |
| 2009 | Not reported | Not reported | 0 of 12 |
| 2010 | Not reported | Not reported | 0 of 12 |
| 2011 | Not reported | Not reported | 0 of 12 |
| 2012 | Not reported | Not reported | 0 of 12 |
| 2013 | Not reported | Not reported | 0 of 12 |
| 2014 | Not reported | Not reported | 0 of 12 |
| 2015 | Not reported | Not reported | 0 of 12 |
| 2016 | Not reported | Not reported | 0 of 12 |
| 2017 | Not reported | Not reported | 0 of 12 |
| 2018 | Not reported | Not reported | 0 of 12 |
| 2019 | Not reported | Not reported | 0 of 12 |
| 2020 | Not reported | Not reported | 0 of 12 |
| 2021 | Not reported | Not reported | 0 of 12 |
| 2022 | Not reported | Not reported | 0 of 12 |
| 2023 | Not reported | Not reported | 0 of 12 |
| 2024 | 4,708 | Not reported | 12 of 12 |
| 2025 | 4,125 | 10.7% | 12 of 12 |
| 2026 (provisional, partial year) | Not reported | Not reported | 0 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free accountNo verified ISO price node is linked to this plant, or its price history could not load.
Emissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| 5653 | Solar Photovoltaic | 4.4 | April 2024 |
| 5653B | Batteries | 4.0 | May 2024 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists FFP NY Goshen Project1, LLC as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Modeled curtailment
A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.
Expected vs reported generation
Monthly modeled expected output and physical potential next to EIA-923 reported output.
300 analyst questions a month, plus MCP
Query FFP - NY Urbanski and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near FFP - NY Urbanski
Questions about FFP - NY Urbanski
How much power does FFP - NY Urbanski produce?
FFP - NY Urbanski reported 4,125 MWh (4.13 GWh) of net generation in 2025, a 10.7% capacity factor on 8.4 MW of nameplate capacity.
Where is FFP - NY Urbanski?
FFP - NY Urbanski is in Orange County, New York, at 41.3309, −74.4034. It is in the New York Independent System Operator balancing area (NYIS).
Who operates FFP - NY Urbanski?
EIA-860M for August 2026 lists FFP NY Goshen Project1, LLC as the operator (EIA operator ID 66147). The operator is not always the owner.
Is FFP - NY Urbanski a solar or a battery storage plant?
Both. Solar capacity totals 4.4 MW and battery storage capacity totals 4 MW.
When did FFP - NY Urbanski start operating?
Its first generator began operating in April 2024, according to EIA-860M.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)