Key facts

Capacity
113 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
October 2025First generator online
Operator
Leeward Asset Management, LLCEIA operator ID 50123
Grid
AZPSBalancing authority AZPS
Price nodes
None linkedNo verified ISO node
Location
Yuma County, AZ32.9942, −113.5098
EIA plant ID
67973EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Sierra Pinta BESS produces

Free · EIA-923

Net generation, 2025

−5.14 GWh

−5,140 MWh, final. 3 of 12 months reported

Battery discharge, 2025

26.6 GWh

Charge 25.6 GWh

January to July 2026

−19.2 GWh

Provisional

Annual net generation, GWh
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
2019Not reportedNot reported0 of 12
2020Not reportedNot reported0 of 12
2021Not reportedNot reported0 of 12
2022Not reportedNot reported0 of 12
2023Not reportedNot reported0 of 12
2024Not reportedNot reported0 of 12
2025−5,140Not reported3 of 12
2026 (provisional, partial year)−19,214Not reported7 of 7

* 2026 covers January to July and is provisional. Battery plants can report negative net generation, when charging uses more energy than they discharge.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
SP01Batteries113.0October 2025

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Leeward Asset Management, LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Sierra Pinta BESS and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Sierra Pinta BESS

More plants operated by Leeward Asset Management, LLC

Questions about Sierra Pinta BESS

How much power does Sierra Pinta BESS produce?

Sierra Pinta BESS reported −5,140 MWh (−5.14 GWh) of net generation in 2025. From January to July 2026 it reported −19.2 GWh, which is provisional. 3 of 12 months were reported for 2025.

Where is Sierra Pinta BESS?

Sierra Pinta BESS is in Yuma County, Arizona, at 32.9942, −113.5098. It is in the Arizona Public Service Company balancing area (AZPS).

Who operates Sierra Pinta BESS?

EIA-860M for August 2026 lists Leeward Asset Management, LLC as the operator (EIA operator ID 50123). The operator is not always the owner.

When did Sierra Pinta BESS start operating?

Its first generator began operating in October 2025, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page