Spirit Mountain
Hydro power plant in Park County, Wyoming. 4.5 MW of nameplate capacity across 1 generator, operated by U S Bureau of Reclamation.
Also known as EIA plant 7541
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 4.5 MWNameplate
- Generators
- 1 operatingEIA-860M, August 2026
- Operating since
- October 1994First generator online
- Operator
- U S Bureau of ReclamationEIA operator ID 2518
- Grid
- WAUWBalancing authority WAUW
- Price nodes
- 1 SPP nodeResource nodes with prices
- Location
- Park County, WY44.5127, −109.1299
- EIA plant ID
- 7541EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Spirit Mountain produces
Free · EIA-923Net generation, 2025
16.1 GWh
16,105 MWh, final
Capacity factor, 2025
40.9%
2024: 43.7%
January to July 2026
Not reported
Provisional. 0 of 7 months reported
Range, 2015 to 2025
15.0–18.4
GWh a year. Low 2017, high 2015
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | 14,757 | Not reported | 12 of 12 |
| 2001 | 19,442 | Not reported | 12 of 12 |
| 2002 | 13,051 | Not reported | 12 of 12 |
| 2003 | 15,374 | Not reported | 12 of 12 |
| 2004 | 16,520 | Not reported | 12 of 12 |
| 2005 | 13,204 | Not reported | 12 of 12 |
| 2006 | 16,303 | Not reported | 12 of 12 |
| 2007 | 16,002 | Not reported | 12 of 12 |
| 2008 | 14,004 | Not reported | 12 of 12 |
| 2009 | 17,603 | Not reported | 12 of 12 |
| 2010 | 16,307 | 41.4% | 12 of 12 |
| 2011 | 14,288 | 36.2% | 12 of 12 |
| 2012 | 17,800 | 45.0% | 12 of 12 |
| 2013 | 16,920 | 42.9% | 12 of 12 |
| 2014 | 16,315 | 41.4% | 12 of 12 |
| 2015 | 18,386 | 46.6% | 12 of 12 |
| 2016 | 16,839 | 42.6% | 12 of 12 |
| 2017 | 15,018 | 38.1% | 12 of 12 |
| 2018 | 15,539 | 39.4% | 12 of 12 |
| 2019 | 17,052 | 43.3% | 12 of 12 |
| 2020 | 16,419 | 41.5% | 12 of 12 |
| 2021 | 15,584 | 39.5% | 12 of 12 |
| 2022 | 15,778 | 40.0% | 12 of 12 |
| 2023 | 16,269 | 41.3% | 12 of 12 |
| 2024 | 17,277 | 43.7% | 12 of 12 |
| 2025 | 16,105 | 40.9% | 12 of 12 |
| 2026 (provisional, partial year) | Not reported | Not reported | 0 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free account · SPPEmissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| 1 | Conventional Hydroelectric | 4.5 | October 1994 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists U S Bureau of Reclamation as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
300 analyst questions a month, plus MCP
Query Spirit Mountain and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Spirit Mountain
More plants operated by U S Bureau of Reclamation
Questions about Spirit Mountain
How much power does Spirit Mountain produce?
Spirit Mountain reported 16,105 MWh (16.1 GWh) of net generation in 2025, a 40.9% capacity factor on 4.5 MW of nameplate capacity.
Where is Spirit Mountain?
Spirit Mountain is in Park County, Wyoming, at 44.5127, −109.1299. It is in the Western Area Power Administration UGP West balancing area (WAUW).
Who operates Spirit Mountain?
EIA-860M for August 2026 lists U S Bureau of Reclamation as the operator (EIA operator ID 2518). The operator is not always the owner.
When did Spirit Mountain start operating?
Its first generator began operating in October 1994, according to EIA-860M.
Does InfraMap have power prices for Spirit Mountain?
Yes. InfraMap has SPP day-ahead and real-time prices at 1 price node linked to Spirit Mountain, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
- SPP day-ahead and real-time prices; node and hub assignments as of 2026-10-05
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page