EIA-860M nameplate capacity and EIA-923 net generation, 2025.On the map
Built from InfraMap's 2025 data with the same tools the analyst uses.
Common mistakes
Using MW as an amount of electricity. A 100 MW plant produces up to 100 MWh in each hour it runs at full power, not 100 MW a year.
Multiplying nameplate MW by 8,760 hours and calling it output. That is the ceiling. Real output depends on how many hours the plant actually runs, which is its capacity factor.
Mixing AC and DC ratings. Solar panels are rated in DC, and the grid sees the lower AC rating of the inverters.
How the InfraMap analyst defines it
The rate of energy production or use. MW is not an energy total. Integrate power over elapsed time for MWh.
Energy MWh = sum of average interval MW times elapsed interval hours
Reviewed October 1, 2026 against the references below. The analyst and the MCP server answer with this definition.