HydroOperatingNYISO

Blake

Hydro power plant in St Lawrence County, New York. 15 MW of nameplate capacity across 1 generator, operated by Erie Boulevard Hydropower LP.

Also known as Blake Power Station · EIA plant 2547

Analyst: free account, 1 question a day.

StarkSouth ColtonHigleyParishvilleBlake5 km
Open in the map
6 plants within 15 km, from EIA coordinates.

Key facts

Capacity
15 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
January 1957First generator online
Operator
Erie Boulevard Hydropower LPEIA operator ID 5914
Grid
NYISOBalancing authority NYIS
Price nodes
1 NYISO nodeResource nodes with prices
Location
St Lawrence County, NY44.5065, −74.7534
EIA plant ID
2547EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Blake produces

Free · EIA-923

Net generation, 2025

48.2 GWh

48,217 MWh, final

Capacity factor, 2025

36.7%

2024: 49.3%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

45.4–75.9

GWh a year. Low 2020, high 2017

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
200153,632Not reported12 of 12
200262,921Not reported12 of 12
200365,238Not reported12 of 12
20045,772Not reported12 of 12
200570,706Not reported12 of 12
200677,034Not reported12 of 12
200760,127Not reported12 of 12
200875,691Not reported12 of 12
200966,887Not reported12 of 12
201059,45445.2%12 of 12
201166,87950.9%12 of 12
201251,39739.0%12 of 12
201364,11648.8%12 of 12
201458,11544.2%12 of 12
201552,24239.8%12 of 12
201651,52839.1%12 of 12
201775,85857.7%12 of 12
201860,61546.1%12 of 12
201975,09057.1%12 of 12
202045,41334.5%12 of 12
202156,76243.2%12 of 12
202259,04244.9%12 of 12
202369,77753.1%12 of 12
202464,94549.3%12 of 12
202548,21736.7%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · NYISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Conventional Hydroelectric15.0January 1957

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Erie Boulevard Hydropower LP as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Blake and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Blake

More plants operated by Erie Boulevard Hydropower LP

Questions about Blake

How much power does Blake produce?

Blake reported 48,217 MWh (48.2 GWh) of net generation in 2025, a 36.7% capacity factor on 15 MW of nameplate capacity.

Where is Blake?

Blake is in St Lawrence County, New York, at 44.5065, −74.7534. It is in the New York Independent System Operator balancing area (NYIS).

Who operates Blake?

EIA-860M for August 2026 lists Erie Boulevard Hydropower LP as the operator (EIA operator ID 5914). The operator is not always the owner.

When did Blake start operating?

Its first generator began operating in January 1957, according to EIA-860M.

Does InfraMap have power prices for Blake?

Yes. InfraMap has NYISO day-ahead and real-time prices at 1 price node linked to Blake, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • NYISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page