HydroOperatingWACM

Green Mountain

Hydro power plant in Summit County, Colorado. 26 MW of nameplate capacity across 2 generators, operated by U S Bureau of Reclamation.

Also known as EIA plant 516

Analyst: free account, 1 question a day.

Williams Fork Hydro PlantDillon Hydro PlantTom Sifers SolarGranby HydroGeorgetown HydroAmerican Gypsum CogenerationGreen Mountain25 km
Open in the map
6 plants within 59 km, from EIA coordinates.

Key facts

Capacity
26 MWNameplate
Generators
2 operatingEIA-860M, August 2026
Operating since
May 1943First generator online
Operator
U S Bureau of ReclamationEIA operator ID 2518
Grid
WACMBalancing authority WACM
Price nodes
1 SPP nodeResource nodes with prices
Location
Summit County, CO39.8788, −106.3327
EIA plant ID
516EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Green Mountain produces

Free · EIA-923

Net generation, 2025

28.5 GWh

28,515 MWh, final

Capacity factor, 2025

12.5%

2024: 25.3%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

24.0–76.6

GWh a year. Low 2022, high 2015

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
200041,608Not reported12 of 12
200130,648Not reported12 of 12
200218,975Not reported12 of 12
200326,187Not reported12 of 12
200420,519Not reported12 of 12
200523,882Not reported12 of 12
200628,884Not reported12 of 12
200761,146Not reported12 of 12
200866,327Not reported12 of 12
200967,130Not reported12 of 12
201050,20922.0%12 of 12
201182,04636.0%12 of 12
201235,91415.7%12 of 12
201333,14914.6%12 of 12
201493,80241.2%12 of 12
201576,64233.7%12 of 12
201659,56826.1%12 of 12
201756,94025.0%12 of 12
201832,03414.1%12 of 12
201968,34130.0%12 of 12
202042,08718.4%12 of 12
202125,87711.4%12 of 12
202224,02410.5%12 of 12
202347,06920.7%12 of 12
202457,76225.3%12 of 12
202528,51512.5%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · SPP

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Conventional Hydroelectric13.0May 1943
2Conventional Hydroelectric13.0May 1943

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists U S Bureau of Reclamation as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Green Mountain and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Green Mountain

More plants operated by U S Bureau of Reclamation

Questions about Green Mountain

How much power does Green Mountain produce?

Green Mountain reported 28,515 MWh (28.5 GWh) of net generation in 2025, a 12.5% capacity factor on 26 MW of nameplate capacity.

Where is Green Mountain?

Green Mountain is in Summit County, Colorado, at 39.8788, −106.3327. It is in the Western Area Power Administration - Rocky Mountain Region balancing area (WACM).

Who operates Green Mountain?

EIA-860M for August 2026 lists U S Bureau of Reclamation as the operator (EIA operator ID 2518). The operator is not always the owner.

When did Green Mountain start operating?

Its first generator began operating in May 1943, according to EIA-860M.

Does InfraMap have power prices for Green Mountain?

Yes. InfraMap has SPP day-ahead and real-time prices at 1 price node linked to Green Mountain, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • SPP day-ahead and real-time prices; node and hub assignments as of 2026-10-05