Key facts

Capacity
167.7 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
January 2002First generator online
Operator
Desert Sky Wind Farm LPEIA operator ID 49796
Grid
ERCOTBalancing authority ERCO
Price nodes
2 ERCOT nodesResource nodes with prices
Location
Pecos County, TX30.9178, −102.0867
EIA plant ID
55992EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Desert Sky produces

Free · EIA-923

Net generation, 2025

541 GWh

541,153 MWh, final

Capacity factor, 2025

36.8%

2024: 33.7%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

400.9–559.1

GWh a year. Low 2017, high 2021

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002360,629Not reported12 of 12
2003373,206Not reported12 of 12
2004397,643Not reported12 of 12
2005468,192Not reported12 of 12
2006488,474Not reported12 of 12
2007484,483Not reported12 of 12
2008472,040Not reported12 of 12
2009381,091Not reported12 of 12
2010512,44036.4%12 of 12
2011491,63935.0%12 of 12
2012446,07631.6%12 of 12
2013459,36432.7%12 of 12
2014503,58935.8%12 of 12
2015439,29531.2%12 of 12
2016420,52129.8%12 of 12
2017400,85828.5%12 of 12
2018422,766Not reported12 of 12
2019528,67236.0%12 of 12
2020539,37836.6%12 of 12
2021559,07738.1%12 of 12
2022482,28932.8%12 of 12
2023462,29431.5%12 of 12
2024496,72133.7%12 of 12
2025541,15336.8%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · ERCOT

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Onshore Wind Turbine167.7January 2002

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Desert Sky Wind Farm LP as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Desert Sky and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Desert Sky

Questions about Desert Sky

How much power does Desert Sky produce?

Desert Sky reported 541,153 MWh (541 GWh) of net generation in 2025, a 36.8% capacity factor on 167.7 MW of nameplate capacity.

Where is Desert Sky?

Desert Sky is in Pecos County, Texas, at 30.9178, −102.0867. It is in the Electric Reliability Council of Texas, Inc. balancing area (ERCO).

Who operates Desert Sky?

EIA-860M for August 2026 lists Desert Sky Wind Farm LP as the operator (EIA operator ID 49796). The operator is not always the owner.

When did Desert Sky start operating?

Its first generator began operating in January 2002, according to EIA-860M.

Does InfraMap have power prices for Desert Sky?

Yes. InfraMap has ERCOT day-ahead and real-time prices at 2 price nodes linked to Desert Sky, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • ERCOT day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)
  • Project names from the USGS U.S. Wind Turbine Database

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page