WindOperatingBPAT

Leaning Juniper

Wind power plant in Gilliam County, Oregon. 110.4 MW of nameplate capacity across 1 generator, operated by PacifiCorp.

Also known as EIA plant 56360

Analyst: free account, 1 question a day.

Leaning Juniper Wind…Arlington Wind Power ProjectWheat Field Wind Power ProjectMontague Wind Power Facility LLCLeaning Juniper5 km
Open in the map
6 plants within 12 km, from EIA coordinates.

Key facts

Capacity
110.4 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
October 2006First generator online
Operator
PacifiCorpEIA operator ID 14354
Grid
BPATBalancing authority BPAT
Price nodes
None linkedNo verified ISO node
Location
Gilliam County, OR45.6525, −120.2098
EIA plant ID
56360EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Leaning Juniper produces

Free · EIA-923

Net generation, 2025

270 GWh

269,522 MWh, final

Capacity factor, 2025

27.9%

2024: 28.4%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

98.2–316.4

GWh a year. Low 2019, high 2020

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
200667,550Not reported4 of 12
2007290,452Not reported12 of 12
2008376,243Not reported12 of 12
2009258,672Not reported12 of 12
2010223,55825.4%12 of 12
2011234,78926.7%12 of 12
2012190,905Not reported12 of 12
2013206,166Not reported12 of 12
2014215,245Not reported12 of 12
2015188,56721.4%12 of 12
2016202,61423.0%12 of 12
2017155,68517.7%12 of 12
2018201,66522.9%12 of 12
201998,159Not reported12 of 12
2020316,36832.6%12 of 12
2021293,64130.4%12 of 12
2022253,40826.2%12 of 12
2023254,65826.3%12 of 12
2024275,21928.4%12 of 12
2025269,52227.9%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Onshore Wind Turbine110.4October 2006

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists PacifiCorp as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Leaning Juniper and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Leaning Juniper

More plants operated by PacifiCorp

Questions about Leaning Juniper

How much power does Leaning Juniper produce?

Leaning Juniper reported 269,522 MWh (270 GWh) of net generation in 2025, a 27.9% capacity factor on 110.4 MW of nameplate capacity.

Where is Leaning Juniper?

Leaning Juniper is in Gilliam County, Oregon, at 45.6525, −120.2098. It is in the Bonneville Power Administration balancing area (BPAT).

Who operates Leaning Juniper?

EIA-860M for August 2026 lists PacifiCorp as the operator (EIA operator ID 14354). The operator is not always the owner.

When did Leaning Juniper start operating?

Its first generator began operating in October 2006, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page