WindOperatingLDWP

Milford Wind Corridor I LLC

Wind power plant in Beaver County, Utah. 203.5 MW of nameplate capacity across 1 generator, operated by Milford Wind Corridor Phase I, LLC (Longroad).

Also known as Milford Wind Corridor I · Milford Phase I · EIA plant 57079

Analyst: free account, 1 question a day.

Milford Wind Corridor Stage II LLCEscalante Solar III, LLCEscalante Solar I, LLCMilford Solar 1BlundellMilford Wind Corridor I5 km
Open in the map
6 plants within 9.1 km, from EIA coordinates.

Key facts

Capacity
203.5 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
September 2009First generator online
Operator
Milford Wind Corridor Phase I, LLC (Longroad)EIA operator ID 65908
Grid
LDWPBalancing authority LDWP
Price nodes
None linkedNo verified ISO node
Location
Beaver County, UT38.5357, −112.9350
EIA plant ID
57079EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Milford Wind Corridor I produces

Free · EIA-923

Net generation, 2025

401 GWh

401,437 MWh, final

Capacity factor, 2025

22.5%

2024: 21.2%

January to July 2026

213 GWh

Provisional

Range, 2015 to 2025

326.3–455.2

GWh a year. Low 2023, high 2016

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
200939,982Not reported2 of 12
2010400,75122.5%12 of 12
2011414,42023.2%12 of 12
2012457,14525.6%12 of 12
2013338,52919.0%12 of 12
2014415,96823.3%12 of 12
2015392,41922.0%12 of 12
2016455,18925.5%12 of 12
2017442,50124.8%12 of 12
2018394,36622.1%12 of 12
2019401,08322.5%12 of 12
2020395,38622.1%12 of 12
2021415,70723.3%12 of 12
2022353,50319.8%12 of 12
2023326,32418.3%12 of 12
2024379,44421.2%12 of 12
2025401,43722.5%12 of 12
2026 (provisional, partial year)212,51120.5%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Onshore Wind Turbine203.5September 2009

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Milford Wind Corridor Phase I, LLC (Longroad) as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Milford Wind Corridor I LLC and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Milford Wind Corridor I

Questions about Milford Wind Corridor I

How much power does Milford Wind Corridor I LLC produce?

Milford Wind Corridor I LLC reported 401,437 MWh (401 GWh) of net generation in 2025, a 22.5% capacity factor on 203.5 MW of nameplate capacity. From January to July 2026 it reported 213 GWh, which is provisional.

Where is Milford Wind Corridor I LLC?

Milford Wind Corridor I LLC is in Beaver County, Utah, at 38.5357, −112.9350. It is in the Los Angeles Department of Water and Power balancing area (LDWP).

Who operates Milford Wind Corridor I LLC?

EIA-860M for August 2026 lists Milford Wind Corridor Phase I, LLC (Longroad) as the operator (EIA operator ID 65908). The operator is not always the owner.

When did Milford Wind Corridor I LLC start operating?

Its first generator began operating in September 2009, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)
  • Project names from the USGS U.S. Wind Turbine Database

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page