Milford Wind Corridor I LLC
Wind power plant in Beaver County, Utah. 203.5 MW of nameplate capacity across 1 generator, operated by Milford Wind Corridor Phase I, LLC (Longroad).
Also known as Milford Wind Corridor I · Milford Phase I · EIA plant 57079
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 203.5 MWNameplate
- Generators
- 1 operatingEIA-860M, August 2026
- Operating since
- September 2009First generator online
- Operator
- Milford Wind Corridor Phase I, LLC (Longroad)EIA operator ID 65908
- Grid
- LDWPBalancing authority LDWP
- Price nodes
- None linkedNo verified ISO node
- Location
- Beaver County, UT38.5357, −112.9350
- EIA plant ID
- 57079EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Milford Wind Corridor I produces
Free · EIA-923Net generation, 2025
401 GWh
401,437 MWh, final
Capacity factor, 2025
22.5%
2024: 21.2%
January to July 2026
213 GWh
Provisional
Range, 2015 to 2025
326.3–455.2
GWh a year. Low 2023, high 2016
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | Not reported | Not reported | 0 of 12 |
| 2006 | Not reported | Not reported | 0 of 12 |
| 2007 | Not reported | Not reported | 0 of 12 |
| 2008 | Not reported | Not reported | 0 of 12 |
| 2009 | 39,982 | Not reported | 2 of 12 |
| 2010 | 400,751 | 22.5% | 12 of 12 |
| 2011 | 414,420 | 23.2% | 12 of 12 |
| 2012 | 457,145 | 25.6% | 12 of 12 |
| 2013 | 338,529 | 19.0% | 12 of 12 |
| 2014 | 415,968 | 23.3% | 12 of 12 |
| 2015 | 392,419 | 22.0% | 12 of 12 |
| 2016 | 455,189 | 25.5% | 12 of 12 |
| 2017 | 442,501 | 24.8% | 12 of 12 |
| 2018 | 394,366 | 22.1% | 12 of 12 |
| 2019 | 401,083 | 22.5% | 12 of 12 |
| 2020 | 395,386 | 22.1% | 12 of 12 |
| 2021 | 415,707 | 23.3% | 12 of 12 |
| 2022 | 353,503 | 19.8% | 12 of 12 |
| 2023 | 326,324 | 18.3% | 12 of 12 |
| 2024 | 379,444 | 21.2% | 12 of 12 |
| 2025 | 401,437 | 22.5% | 12 of 12 |
| 2026 (provisional, partial year) | 212,511 | 20.5% | 7 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free accountNo verified ISO price node is linked to this plant, or its price history could not load.
Emissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| 1 | Onshore Wind Turbine | 203.5 | September 2009 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Milford Wind Corridor Phase I, LLC (Longroad) as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Modeled curtailment
A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.
Expected vs reported generation
Monthly modeled expected output and physical potential next to EIA-923 reported output.
300 analyst questions a month, plus MCP
Query Milford Wind Corridor I LLC and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Milford Wind Corridor I
Questions about Milford Wind Corridor I
How much power does Milford Wind Corridor I LLC produce?
Milford Wind Corridor I LLC reported 401,437 MWh (401 GWh) of net generation in 2025, a 22.5% capacity factor on 203.5 MW of nameplate capacity. From January to July 2026 it reported 213 GWh, which is provisional.
Where is Milford Wind Corridor I LLC?
Milford Wind Corridor I LLC is in Beaver County, Utah, at 38.5357, −112.9350. It is in the Los Angeles Department of Water and Power balancing area (LDWP).
Who operates Milford Wind Corridor I LLC?
EIA-860M for August 2026 lists Milford Wind Corridor Phase I, LLC (Longroad) as the operator (EIA operator ID 65908). The operator is not always the owner.
When did Milford Wind Corridor I LLC start operating?
Its first generator began operating in September 2009, according to EIA-860M.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
- Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)
- Project names from the USGS U.S. Wind Turbine Database
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page